Aller au contenu

Cette page n'est pas encore traduite ; elle s'affiche en anglais. Page en anglais.

CAPEX UAT Guide — from 2D drawings to the dashboard

⬇ Download the PDF The PDF is made from this page each time it is published, and checked: the checklist on a sheet of its own, each chapter on a new page, no table row split or cut off. Print it, tick the boxes by hand, sign the last page and hand it in.

Document control

Document CAPEX UAT Guide — from 2D drawings to the dashboard
Purpose The step-by-step test script for the User Acceptance Test of the pilot client (Sysnova): BIM drawings to a priced model, the ERP exercise, the CAPEX dashboard
Revision 2026-11-23 (j)
Status Issued for UAT. Proven step by step by the UAT Dry Run of 2026-11-19 (86 of 86 steps PASS, the 80 steps of this guide and the 6 setup steps of the Developer Guide §3); the dry-run report is issued separately and stays as signed. Since then, steps were corrected: the change list after this cover (items 22 to 30) names each step and what changed.
Prepared and issued by Redhuan D. Oon, Project Consultant
For The pilot client's UAT team: System Setup, BIM, Project Mgmt Accounting
The latest copy Page: red1oon.github.io/BIMCompiler/CapexUATGuide · PDF: CapexUATGuide.pdf. The PDF is made from the page at every publish and checked (pages, links).

Changes since the signed UAT report: listed on the next page. Read them even if you have already done the UAT.

Revision history

Revision What changed
2026-11-23 (h) to (j) The whole Shed into the ERP and the dashboard: B4, L1 to L3 before C, D (item 27); the link names the order, Push again? (item 28); L2's status line, B5.1's pack date (items 29, 30)
2026-11-22 (g) One cost for the model: B3.1, B5 and the reference pack (item 26)
2026-11-22 (c) to (f) Items 9 to 19 moved into their steps; items 22 to 25; film part 3 re-published, linked (item 20)
2026-11-22 (b) Legacy iDempiere: A5, L1 to L3 (item 21). No step changed
2026-11-22 Change list item 20 and See how item 3: film part 3, linked. No step changed
2026-11-21 Change list items 9 to 19 (film part 3). No step changed
2026-11-20 (b) Change list item 8 and See how item 2: film part 2, linked. No step changed
2026-11-20 Pages Changes since…, What is this? (How do I pass?), Contents, See how; short tables kept whole; A3.1 Pack In window; B3.1 second currency
2026-11-19 This cover; each section on a new page; page numbers; every link in the PDF opens the public site
2026-11-18 Dry-run corrections: A1 links Developer Guide §3; D2b, D3, D8 fresh-GardenWorld figures; D9 30-minute refresh; B4.4 Task Line
2026-11-15 Roles and the checklist sheet; B00 export from BricsCAD; B0 from the sheets as drawn to the marked set; B3.1 measured total cost; B5 mark your run with the reference pack; the PDF
2026-11-14 Corrections from the full dry run: window names and menu paths, chapter C step by step, C4 Issue to Project, construction products at standard cost, chapter B on the Shed drawing set
2026-11-13 First issue

Changes since the signed UAT report (2026-11-19)

Read these even if you have already done the UAT. If your run met one of them, retest that step. They go into the report's appendix; the signed report itself is not changed.

# Step What Status What to do
1 B5.2, B5.3 The UAT Run Checker wrongly read box 3 (your database) as FAIL: tables differ, project_metadata 4 vs 5 when you skipped the optional Accept all (B2.2c). Fixed 2026-11-19, live If you saw that FAIL: reload the Run Checker and mark your run again with the same files
2 PDF download Right after the site is updated, ⬇ Download the PDF can fail once (Failed - Unknown server error, the file saved as .html). Noted Wait a minute and click again; the PDF is a few MB
3 A3.1 This step's Confirm described only the folder script. The Pack In window ends with the Process Message Processed=225 Un-Resolved=0. Corrected in this revision If you used the window, that message is a pass
4 B4, D The USD amount reaches the Project Order unchanged (B4.1, B4.2, B4.4). It is as correct as the shipped rate pack, not a market price. Chapter D's dashboard reads the GardenWorld test projects, not the Shed. Noted None
5 B3.1 The amount in brackets is the rate pack's second currency (RM), whatever language you choose. Showing your local currency for the language you choose is ongoing development. Noted, in development Compare the USD figure
6 (film) The hands-on film shows the ready-marked sheets. The raw-sheet path (B0: mark the sheets yourself, then Arrange) is to follow. Noted None; B0 is unchanged
7 A2.2, A3.1, C (log in) After you log in as GardenAdmin, Chrome may show its own window Change your password: the password you just used was found in a data breach. That is Chrome's warning about the well-known demo password, not an iDempiere error. Until you close it, clicks on the page do nothing. Noted Press OK on Chrome's window, then go on
8 B0, B2.3, B5 (film) The film UAT, hands on, part 2 shows the path item 6 said was to follow: the nine sheets as drawn, marked by hand (B0.1 to B0.9), Arrange (B2.3), and the Run Checker with your nine marked copies in box 2 (B5): every row and the run read PASS. Film published: youtu.be/WvPgjcMbSwo None; B0 is unchanged. Watch it before you mark the sheets yourself
9 C (log in) The guide names no organization. With the default * a purchase order will not save: Fill mandatory fields: Organization, Warehouse. Corrected in the step (2026-11-22 (c)) Follow chapter C's log in note: it now says this
10 C1.1, D4 The order window prices a line to the Purchase list's 2 decimals (68.1167 becomes 68.12), so an order total differs from quantity × standard cost (TD_RIVERSIDE 1,975.48, not 1,975.38; TD_DATAHALL 1,807.92, not 1,799.55, as 1.075 becomes 1.08). D4's Open purchase orders then reads USD 6,741.25, not 6,738.39. D2b and D3 are not affected (an issue uses the standard cost). Corrected in the step (2026-11-22 (c)) Follow the step: it now says this
11 C2.1 Create lines from lists no lines on this iDempiere build (its search binds the wrong field to the order). Corrected in the step (2026-11-22 (c)) Follow the step: it now says this
12 C3.2 The Business Partner search of the Payment window opens with Vendor = No, so no vendor is listed. Corrected in the step (2026-11-22 (c)) Follow the step: it now says this
13 C (log in) Chrome's Save password? stays open after you log in and takes the keys meant for the page. Corrected in the step (2026-11-22 (c)) Follow chapter C's log in note: it now says this
14 C4.1, C5.1, D6 The test projects have Line Level = Project; the Project window then hides the Phase tab. Corrected in the step (2026-11-22 (c)) Follow the step: it now says this
15 C4.4 Project Balance shows 4 decimals (204.3501, 577.625); the guide prints them rounded (204.35, 577.63). Corrected in the step (2026-11-22 (c)) Follow the step: it now says this
16 C5.1 After you tick Complete, Save is refused: Fill mandatory fields: Invoice Rule. The test data's phases carry none. Corrected in the step (2026-11-22 (c)) Follow the step: it now says this
17 C5.1 The Phase tab is a list under the header. Corrected in the step (2026-11-22 (c)) Follow the step: it now says this
18 D3 Adding up the panel's Spent column gives 2,020.46; the tile reads 2,020.45 (each row is rounded to the cent). Corrected in the step (2026-11-22 (c)) Follow the step: it now says this
19 C4.2 Each Issue to Project opens its own window tab; after several, the first tabs are pushed off the strip. Corrected in the step (2026-11-22 (c)) Follow the step: it now says this
30 B5.1 The reference pack of revision (g) (Shed_UAT_pack_20261122.zip) reads Pack intact: 19 files checked, built 2026-11-22 … under box 1; the step still said built 2026-11-15 (the earlier pack). Corrected in this revision If box 1 showed 2026-11-22, that is a pass
29 L2 L2's status line in full. On a fresh iDempiere the first push also creates the Shed's product categories, products and unit, so the line reads iDempiere Project #… · created {"categories":3,"products":11,"projects":1,"phases":6,"tasks":8,"lines":11,"uoms":1}. Revision (i) quoted only the project's counts, measured on a server that already held those products. Measured twice on a reset test instance (2026-11-23). Corrected in this revision If L2 showed the longer line, that is a pass
28 B4.2 to B4.4, L2, L3 The ERP link names its Project Order. The Viewer's link after a push now reads SHED #… ↗ (the order's id), not open ↗; on a legacy iDempiere it appears only after your push, with the number of the status line. Pressing › ERP again first shows a box Push again? (Cancel or Push again); a second push adds nothing, on the Kernel ERP and on a legacy iDempiere alike (measured 2026-11-23: three pushes, one project SHED). The films still show open ↗. Corrected in this revision None if you passed B4 or L; the steps now name the link and the box
27 B4, L1 to L3, D The whole Shed reaches the ERP and the dashboard. B4.1 now sends the whole model: press F, click Level 1 (511), › ERP (USD 355,097.98, B3.1's total), not one group of parts. On a legacy iDempiere, L1 to L3 come before chapter C, so chapter D shows SHED beside the test projects: 15 projects, Approved Budget USD 359,765.78, Not started 6, Actual Cost 1 % of plan, Home 15 and 359,766. Measured on a fresh run in that order (2026-11-23). Item 4's the dashboard reads the test projects, not the Shed no longer holds. The films show one group and the 14-project figures. Corrected in this revision Redo B4 (or L1 to L3), then read D again
26 B3.1, B5 One cost for the model. The Viewer showed two costs for the Shed: total cost in the Find panel priced each part at its rate × the number of parts (USD 96,839), while the Find bar and › ERP priced it at its rate × its quantity in the rate's own unit (m, m², m³). There is now one cost, in the rate pack's own units: USD 355,097.98 (RM 1,365,761), the same in total cost, the Find bar and the Project Order. The Run Checker reads the cents; the reference pack is rebuilt with the new figure (Shed_UAT_pack_20261122.zip). The films still show the old figure (USD 96,839); the guide's figure is the one to confirm. Corrected in this revision Redo B3.1, then B5 with the new pack
25 B4.1, C3.1, C3.2, D A fourth independent check of the film part 3: B4.1 the Find list fills only when you search (click the model, F, type a word such as column, Enter; revision (d) wrongly said it shows parts at once); C3.2 type the vendor's search key SeedFarm (the Payment window does not find it by name); C3.1 the dialog's own Create lines from button, not the header's; D's read job ends with a line §DASH_LEGACY_READ_VERDICT PASS …. Corrected in this revision Retest a step of this list if you did it before
24 B4.1, C3.1, D2, D9, sign-off A third independent check of the film part 3: C3.1 says Save before Create lines from (no second Save); D9 says Log Out, then log in with Select Role and HQ; B4.1 names the key F; D2's ERP ↗ may ask you to log in; the checklist and sign-off count the legacy-only steps (A5, L1 to L3). Corrected in this revision Retest a step of this list if you did it before
23 B4.1, L, C3.1, C3.2, C5.1, D8, D9, C (log in) A second independent check of the film part 3 against this guide: do the legacy L1 to L3 after chapter D (or on a copy: SHED is one more project); L3 and the chapter C log in name Chrome's windows, the demo password and closing each document's tab; C3.1 runs with the window's own Create lines from button; C3.2 half paid is rounded up to the cent; C5.1 says what to do with no Phase tab; D9 money goals are rounded to the unit; B4.1's list shows parts at once. Corrected in this revision Retest a step of this list if you did it before
22 C1.1, C2.1, C3.2, C4.1, C4.2, C4.4, C5.1, D3, D4, D9 and L3 The steps now say what works. Items 9 to 19 were written only in this list; each is now in its step, so a step read on its own passes (C5.1 was the one that stopped a tester: Save refused, Fill mandatory fields: Invoice Rule). Also new in D: the read job ends with §DASH_LEGACY_READ_VERDICT PASS and needs BRIDGE_USER/BRIDGE_PASS on a server that is not localhost; D9 says what the Home goals' percents are measured against (the targets A2 installs), so Actual Cost reads 0 % on the test data. Found by an independent check of the film part 3 against this guide. Corrected in this revision Retest a step of this list if you did it before
21 A5, B4 If your ERP is a legacy iDempiere: the administrator installs the BIM OOTB plugin (A5, steps LA1 to LA4); then B4 from the Viewer that your iDempiere serves, steps L1 to L3 under B4. The Viewer keeps your sign-in ids when you open a file, and open ↗ opens your iDempiere's Project. New in this revision Only with a legacy iDempiere: A5, then L1 to L3
20 B4, C, D (film) The film UAT, hands on, part 3 shows B4, every document of chapter C made by hand, chapter D, and last the legacy B4 (L1 to L3). Items 9 to 19 are what it met on the way. Film published: youtu.be/g7FTNnbbybA (2026-11-22, follows revision (f); replaces the first upload) None; no step changed. Watch it before chapter C

What is this?

A hands-on test script for the testers of the pilot client (Sysnova). Each step says what to do, what you should see, and has a box to tick. A value is affirmed at its source, not trusted. Wherever a step gives a number, it also says Source: where the number is kept (a record, a field, a formula) and what to open to see it there. Open that source, read the value yourself, and tick Pass only if it matches. A figure on the dashboard is never the evidence: the rows behind it are.

Work top to bottom: every chapter uses what the one before produced. Write anything that differs on the Notes line at the end of each chapter.

Dates in the test data are set for 13 November 2026. Testing well after that day still works, but the colours on the dashboard (on time, late, over budget) drift with the calendar.

How do I pass?

Do every step and tick its box. Your run is then marked in step B5 · Mark your run, the last section of chapter B (B5.1 to B5.4). It is a step of this guide like any other, not a separate task.

In B5 you open the UAT Run Checker, give it the files and the two lines your own run produced, and press Mark my run. It compares them with the reference pack, a run already proven correct, and reads PASS, FAIL or NOT GIVEN for each one. It works in your browser: nothing is uploaded. Then press Download result.

Your final goal is that file, uat_result.json: attach it to your signed sheets and send both back to the person who runs the UAT. A box you leave out reads NOT GIVEN, never PASS. A tester who skipped B00 and B0 gets PARTIAL PASS, which is expected (B5.3).

See how

Films of the steps, on a real screen:

  1. UAT, hands on: where to click: https://youtu.be/PBp4qfV4mIo. From the downloads to B5 and the result file.
  2. UAT, hands on, part 2: https://youtu.be/WvPgjcMbSwo. A3.1 Pack In, then B0 on the nine sheets as drawn (marked by hand), B2.3 Arrange, and B5 with all four rows PASS.
  3. UAT, hands on, part 3: https://youtu.be/g7FTNnbbybA. B4 the model to the ERP, chapter C with every document made by hand in the iDempiere windows, chapter D on the dashboard, and last B4 to a legacy iDempiere (L1 to L3). It follows this revision of the guide.

Contents

Checklist: who does what

Three roles run this test. Tick a part when all its steps pass, and initial it.

Role Who Needs
System Setup your iDempiere administrator psql and a server restart, the GardenWorld Admin login, Node.js (D's read job)
BIM a BIM / QS tester; your drafter for B00 a desktop browser; the drafter: BricsCAD
Project Mgmt Accounting a project / accounting user the GardenWorld Admin login, a desktop browser

Order: System Setup first. BIM may start at once (public apps); on a legacy iDempiere, L1 to L3 before C. Project Mgmt Accounting after A; D after C.

Part Role Done in Needs first Hands over Steps Done / initials
A1 · Own web copy (optional) System Setup web server — your copy of the apps 4 ☐
A2 · Install the dashboard System Setup psql, server restart — the dashboard's scripts in iDempiere 3 ☐
A3 · Load the test data System Setup Pack In, psql A2 12 projects, 10 products 6 ☐
A4 · ERP model check System Setup iDempiere A3 vendor, stock, products 4 ☐
A5 · Plugin (legacy only) System Setup server, Role window — the Viewer at /bimootb 4 ☐
B00 · Export the sheets as DXF BIM (drafter) BricsCAD the drawing nine .dxf 3 ☐
B0 · To the marked set BIM Modeller B00 or pack sheets/ nine _marked.dxf 11 ☐
B1 · The sheets one at a time BIM Modeller B0 — 4 ☐
B2 · Arrange and convert BIM Modeller, Viewer B0 SHED_extracted.db 11 ☐
B3 · 4D and 5D BIM Viewer B2 total cost, finish date 6 ☐
B4 · Project Order BIM Viewer, browser ERP B2 project SHED 4 (legacy: L1–L3) ☐
B5 · Mark your run BIM Run Checker B0.9 B2.8 B2.9 B3.1 uat_result.json 4 ☐
C1 · Purchase orders Project Mgmt Accounting iDempiere A3, A4 orders 2 ☐
C2 · Material receipt Project Mgmt Accounting iDempiere C1 goods received 1 ☐
C3 · Invoice and payment Project Mgmt Accounting iDempiere C2 invoices, payments 2 ☐
C4 · Issue to site Project Mgmt Accounting iDempiere A3 project spending 4 ☐
C5 · Tick a phase Project Mgmt Accounting iDempiere A3 a phase completed 1 ☐
D · The dashboard Project Mgmt Accounting browser C; read job (System Setup) figures signed off 10 ☐

Steps: A 17 · B 43 (29 if given the marked copies: skip B00, B0) · C 10 · D 10, as on the sign-off.

What you need

Item Where
A desktop browser (Chrome, Edge or Firefox) —
The BIM apps the public site red1oon.github.io/bim-ootb, or your own copy (chapter A1)
What to install on your own machine first (git, Node.js, Python 3, a browser; VS Code only for developers) Developer Guide §3
Your iDempiere, with its GardenWorld client and a GardenWorld Admin login your server
The test-data pack 202611131200_GardenWorld_CAPEXTestData.zip
The construction-products script (10 materials at standard cost) 202611141500_CAPEX-TD-CONSTRUCTION-PRODUCTS.sql
The dashboard's scripts for iDempiere listed in chapter A2, all in the bim-ootb repository
The Shed drawing set: nine 2D sheets as DXF files, one per sheet exported from BricsCAD by your drafter as in chapter B00 (a .dwg cannot be opened); chapter B0 then turns them into the nine …_marked.dxf files that chapters B1 onward open (a tester given the …_marked.dxf copies skips B00 and B0)
The reference pack (to mark your run, chapter B5) Shed_UAT_pack_20261122.zip: the nine sheets as B00 exports them, the supplied marked copies, the reference Viewer database and the expected values
The UAT Run Checker check.html in your browser: it reads your files locally, nothing is uploaded

The nine Shed sheets are the pilot client's own work, so its testers may use them. Any other drawing set goes through the same way once its sheets carry their settings (levels, datums and layer meanings), which the Modeller's Drawing metadata panel records.

Where to find each window. Every window and process below is in iDempiere's left-hand menu; open the folder and click the entry, or type the name in the menu's Search box. A new record is made with the New button in the toolbar, saved with Save, and a document is finished with its Document Action button (choose Complete, then OK).

Name used in this guide Menu path
Pack In Application Dictionary ▸ Application Packaging ▸ Pack In
Accounting Schema Performance Analysis and Accounting ▸ Accounting Rules ▸ Accounting Schema
Performance Measure Calculation Performance Analysis and Accounting ▸ Performance Measurement ▸ Performance Measure Calculation
Business Partner Partner Relations ▸ Business Partner Rules ▸ Business Partner
Product Material Management and Pricing ▸ Material Management Rules ▸ Product
Warehouse and Locators Material Management and Pricing ▸ Material Management Rules ▸ Warehouse and Locators
Project Project Management ▸ Project
Issue to Project (a process) Project Management ▸ Issue to Project
Project (Lines/Issues) Project Management ▸ Project (Lines/Issues)
Purchase Order Requisition-to-Invoice (Purchasing) ▸ Purchase Order
Material Receipt Requisition-to-Invoice (Purchasing) ▸ Material Receipt
Purchase Invoice and Credit/Debit Note Requisition-to-Invoice (Purchasing) ▸ Purchase Invoice and Credit/Debit Note
Payment and Receipt Open Items (Financial Movements and Aging) ▸ Payment and Receipt

Who does what: see the checklist sheet above.


A · Set up (System Setup, once)

A1 · The BIM apps on your own server (optional)

The Modeller, the Viewer, the Kernel ERP and the dashboard are plain web files: no application server and no database server. Use the public site, or serve your own copy.

Setting up your own copy from nothing (what to install first: git, Node.js, Python 3 and a browser; how to download the code, serve it, open the three apps and, for developers, set up VS Code) is written once, in the Developer Guide, §3 Start from scratch. Follow it first if your machine is new to the project. Steps A1.1 to A1.4 below are the same download-and-serve steps, with what to confirm for this exercise. Installing iDempiere and its PostgreSQL database is not covered by either guide: chapter A2 onward starts from an iDempiere you already run.

# Do Confirm on screen Result
A1.1 Copy the repository: git clone https://github.com/red1oon/bim-ootb A folder bim-ootb with index.html, modeller/, erp/, capex/ ☐ Pass ☐ Fail
A1.2 Serve the folder with any static web server, for example python3 -m http.server 8080 inside it The server says it is listening ☐ Pass ☐ Fail
A1.3 Open http://<your-server>:8080/index.html. On a first visit the page is a picture with two pills: click the red one Three doors appear under choose your door. Hold the pointer on each to read its name: Buildings / IFC, BIM Modeller, ERP ☐ Pass ☐ Fail
A1.4 Open /capex/index.html on your server The dashboard opens on its built-in sample store (3 projects). The computed tiles read no data (CAPEX PA rows not installed): that is correct until the page reads your iDempiere (chapter D) ☐ Pass ☐ Fail

The large building databases are not stored in the repository. To open the sample buildings from your own server, ask us for the files and place them as the Viewer guide says.

A2 · Install the dashboard into your iDempiere

All scripts are iDempiere migration scripts (PostgreSQL), written for the GardenWorld client. Apply them with psql in file-name order, run update_sequences(), then restart the server: iDempiere keeps web-service types and measures in memory.

Folder in the repository Script(s) What it adds
capex/legacy/ws/migration 202611042300_CAPEX-WS-READ.sql Read-only web-service types for the dashboard's tables, and the role allowed to use them
capex/legacy/ws/q4 202611111400_CAPEX-WS-Q4.sql Reading purchase orders and project issues
capex/legacy/ws/chain 202611121700_CAPEX-WS-CHAIN.sql Reading receipts, vendor invoices and payments (the supply-chain view)
capex/legacy/ws/pacalc 202611131400_CAPEX-WS-PACALC.sql Reading the dashboard's own formulas (Performance Analysis measures) from your server
capex/legacy/migration every script, in name order (202611031900_CAPEX-R0.sql … 202611141000_CAPEX-FORECAST-PROJECTS.sql) The dashboard's formulas as Performance Analysis measures, the Home tab goals, their targets and colours. Money goals show the currency of your login
BIM Document plugin see Installing it Drawings filed against projects (optional for this test)
# Do Confirm on screen Result
A2.1 Apply the scripts above, run update_sequences(), restart iDempiere Each script ends without an error; the server comes back ☐ Pass ☐ Fail
A2.2 Log in as GardenWorld Admin, open the Home tab The Performance panel shows CAPEX goals, for example CAPEX Total Projects, CAPEX Approved Budget ☐ Pass ☐ Fail
A2.3 Open the window Performance Measure Calculation Rows named CAPEX … are there; their SQL can be read and edited here. This is where the dashboard’s formulas live ☐ Pass ☐ Fail

Each script carries a Restore line at its top that removes what it adds.

A3 · Load the test data (GardenWorld)

The pack holds 12 projects (Value TD_…, names ending (test data)) with 42 phases, 84 tasks, 84 planned lines, some phases already ticked complete, and 2 test products. It holds no documents and none of the construction materials: those come from the script in A3.6: you make the orders, receipts, invoices, payments and issues yourself in chapter C. The data can stay in GardenWorld after the test.

The pack goes to the client named in its file name (GardenWorld), and is packed in by that client's administrator.

# Do Confirm on screen Result
A3.1 Put the zip in an empty folder on the server and run utils/RUN_ApplyPackInFromFolder.sh <folder>, or use the Pack In window logged in as GardenWorld Admin (choose the zip, then run it). In the window: New, type a name, Save; the paperclip (Attachment) ▸ Load the zip ▸ OK; then the PackIn button ▸ OK The run prints Successful application of …CAPEXTestData.zip, Error=false and ends with Done. The log also prints a java.lang.Exception trace for each planned line (MProduct.loadPO: NO Data found): these do not stop the run, and the rows are checked in A3.2 to A3.4. With the Pack In window, the Process Message reads Processed=225 Un-Resolved=0 ☐ Pass ☐ Fail
A3.2 Open the Project window, search Value TD_% 12 projects, for example TD_RIVERSIDE – Riverside Tower (test data) Source: the pack file itself holds 12 C_Project records; the window’s record count (status bar) is the count in your database ☐ Pass ☐ Fail
A3.3 Open TD_RIVERSIDE, tab Phase 5 phases with dates; the first 3 are ticked Complete Source: the Phase tab’s own Complete tick boxes (the pack set them); count them yourself ☐ Pass ☐ Fail
A3.4 Look at the project’s Currency The currency of GardenWorld’s Purchase price list. The pack sets no currency: iDempiere takes it from the price list, so it follows your setup ☐ Pass ☐ Fail
A3.5 Pack the same zip in a second time No new projects: still 12. The folder run says the pack is already installed and skips it ☐ Pass ☐ Fail
A3.6 Apply the products script with psql (it can be applied twice: the second run adds nothing), then restart iDempiere: the accounting schema is kept in memory. The script makes 10 Construction products at the Schedule of Rates prices and sets GardenWorld's primary accounting schema (GardenWorld US/A/US Dollar) to Standard costing, because iDempiere costs a project issue by the schema's method. Its first lines hold the Restore line The script ends without an error. Accounting Schema window: GardenWorld US/A/US Dollar, Costing Method Standard ☐ Pass ☐ Fail

A4 · ERP model setup, where needed

GardenWorld already has the vendor, the warehouse and the locator; the products come from A3.6. Check them before chapter C:

# Do Confirm on screen Result
A4.1 Business Partner window: find a vendor (for example Seed Farm Inc., the one this guide uses) At least one partner with Vendor ticked ☐ Pass ☐ Fail
A4.2 Product window: search Value PWD-%, then open PWD-04.2 Brick masonry 10 products in category Construction. PWD-04.2: unit M3, stocked, price 68.1167 on the Purchase price list (tab Price; 8,174 BDT ÷ 120), and a Standard cost of 68.1167 (tab Costs) Source: the product’s Description field names it: PWD SoR 2022 item 04.2, page …, 8174 BDT/M3 = 68.1167 USD at 120. That is the Public Works Department Schedule of Rates item; read the rate and the item number there and divide by 120 yourself ☐ Pass ☐ Fail
A4.3 Warehouse and Locators window: open HQ Warehouse, tab Locator It has the locator Default HQ Locator, where you receive and issue ☐ Pass ☐ Fail
A4.4 Product window: Test material A (test data) The pack’s product exists, in category TD Materials (test data) ☐ Pass ☐ Fail

A5 · The BIM OOTB plugin (only if your ERP is a legacy iDempiere)

Skip A5 if the BIM tester sends the Project Order to the Kernel ERP (B4). With a legacy iDempiere 13, B4 is done from the Viewer that your iDempiere serves (the BIM tester's steps L1 to L3), and that Viewer comes from this plugin. (Why: a browser does not let a page from another site call your iDempiere, so the Viewer is served by the iDempiere itself.) The plugin's source and its build script are in iDempiereOOTB/ of the BIMCompiler repository. You need JDK 17 (javac) and a copy of the bim-ootb repository (the Viewer it packs). Take a database backup first if you want to go back exactly: removing the plugin later leaves the rows its setup pack wrote.

# Do Confirm on screen Result
LA1 Build the two bundles: iDempiereOOTB/org.idempiere.bimootb/tools/build_bundle_poc.sh <your iDempiere>/server <your bim-ootb copy> <an empty folder> Its last line starts §BIMOOTB_BUNDLE and names 2pack=2Pack_13.1.0.zip. The folder holds two folders: org.idempiere.bimootb_13.1.0.<stamp> and org.idempiere.bimootb.viewer_13.1.0.<stamp> ☐ Pass ☐ Fail
LA2 Stop iDempiere. Copy both folders into server/plugins/. Add one line for each to server/configuration/org.eclipse.equinox.simpleconfigurator/bundles.info: org.idempiere.bimootb,13.1.0.<stamp>,plugins/org.idempiere.bimootb_13.1.0.<stamp>/,4,true and the same for org.idempiere.bimootb.viewer. Start iDempiere The plugin packs in its own setup pack a little after the login page answers (up to 3 minutes). Then the Role window lists the role BIM OOTB Push ☐ Pass ☐ Fail
LA3 Role window: open the role the BIM tester logs in with (GardenWorld: GardenWorld Admin), tab Included role templates, New, choose BIM OOTB Push, Save. Then restart iDempiere The tab lists BIM OOTB Push. (Without it the push is refused: Login role does not have access to the service type 'BIMOOTB_Query_C_Project') ☐ Pass ☐ Fail
LA4 Open your iDempiere/bimootb/viewer/viewer.html in a browser The Viewer opens. Give the BIM tester this address, with the user and ids of the role from LA3 (L1) ☐ Pass ☐ Fail

Notes (chapter A): __________


B · BIM: the Shed, from 2D drawings to a priced model (BIM)

This chapter uses your own Shed drawing set: the single-storey farm shed, drawn as nine 2D sheets. You will see each drawing on its own first, then the nine arranged in place, then the 3D model built from them.

The drawings are shortened, so the model is too. The real shed is 410 ft × 50 ft (124.97 m × 15.24 m): 41 bays of 10 ft, grid lines 01 to 42. The drawings show only grids 01–06 and 35–42, with the expansion joint drawn between 06 and 35; the length dimension is drawn 130 ft long and its text is written over to read 410'-0". The Modeller builds what is drawn: 13 bays, 39.62 m long. Every quantity and cost in B2b to B4 is for those 13 bays, about a third of the real shed's length. The 50 ft width is drawn to scale.

The pictures were taken from the real Modeller with these same nine files. The label at the top of each picture and the red ring around a button were added for this guide; in the canvas-only pictures the drawing lines are shown at full strength so that they print clearly.

The nine sheets. From B1 on you open the …_marked.dxf copies: they carry the levels, heights and layer meanings the Modeller needs. You make them yourself from the nine sheets as drawn in B0; the result is the same, mark for mark, as the copies supplied for this test.

Sheet file What it is Role the Modeller shows
0_FLOOR_PLAN_marked.dxf Floor plan PLAN
3_BEAM_LAYOUT_marked.dxf Beam layout PLAN
4_FOUNDATION_LAYOUT_marked.dxf Foundation layout PLAN
1N_ELEV_NORTH_marked.dxf North elevation ELEV
1S_ELEV_SOUTH_marked.dxf South elevation ELEV
2_ELEV_WEST_marked.dxf West elevation ELEV
7_ELEV_EAST_marked.dxf East elevation ELEV
8_SECTION_AA_TRUSS_marked.dxf Section A-A, the roof truss SECTION
5_DETAILS_marked.dxf Details and general notes NOTES

B00 · For the drafter: export the nine sheets from BricsCAD as DXF

This step is for whoever holds the drawing in BricsCAD. Send the testers DXF files, one per sheet, not the .dwg: the Modeller opens .dxf files only. BricsCAD writes a DXF with its DXFOUT command, whose options are Entities (which entities to export), Binary (leave it off: the file is then written as ASCII text), Version, and the number of decimal places (see the BricsCAD help for DXFOUT).

Settings

Setting Use Why
File type DXF, ASCII (text) A binary DXF is refused by the Modeller
DXF version 2018 (any of 2000, 2004, 2007, 2010, 2013, 2018 gives the same model) R12 is refused: it has no drawing units and no hatches, and the gable walls are hatches
Files one DXF per sheet The whole drawing in one file gives no model: the Modeller cannot tell the sheets apart
Drawing units Inches (system variable INSUNITS; the Shed drawing already has it) A file without its units gives no model
Decimal places 16 (the most DXFOUT offers) keeps the coordinates as exact as in the drawing
Position as drawn: do not move, rotate or scale a sheet before exporting it B0 types levels and one box in the drawing's own coordinates
Layers, dimensions, hatches as drawn: do not explode, rename or merge them The Modeller reads the grid lines from the dimensions, the gable walls from the hatches, and each element type from its layer name (B0.4)
# Do Confirm on screen Result
B00.1 Open the Shed drawing in BricsCAD. Check that the drawing units are Inches INSUNITS reads 1 (Inches) ☐ Pass ☐ Fail
B00.2 For each row of the table below: type DXFOUT, choose Entities, select everything inside that sheet's frame (a window from one corner of the frame to the other), and confirm. Leave Binary off, choose version 2018 and 16 decimal places, and save under the file name in the table One .dxf file per row, nine in all ☐ Pass ☐ Fail
B00.3 Send the nine .dxf files to the testers The testers open them in B0.1, which is the check: All defaults must list 34 yellow rows, then 113 after B0.2. Other counts mean the export differs from the drawings this guide was proven on: check the settings above and export again ☐ Pass ☐ Fail
Frame in the drawing (its title) Save as
Shed Floor Plan 0_FLOOR_PLAN.dxf
Beam Lay out Plan 3_BEAM_LAYOUT.dxf
Foundation Lay out Plan 4_FOUNDATION_LAYOUT.dxf
North and South Elevation (one frame, two drawings): the upper drawing, North 1N_ELEV_NORTH.dxf
the same frame, the lower drawing, South 1S_ELEV_SOUTH.dxf
West Elevation 2_ELEV_WEST.dxf
East Elevation 7_ELEV_EAST.dxf
Section A-A (Truss Detail) 8_SECTION_AA_TRUSS.dxf
the details frame (footing, column and grade-beam casting ratios, long sections of the beams) 5_DETAILS.dxf

The general Section A-A frame is not used in this test.

Proven by measurement (witness W-UAT-SHED-SOURCE, 2026-11-15) with files written in each DXF version by a DXF library, not by BricsCAD itself: ASCII 2000 to 2018 give the same model, 512 bodies, identical; R12, binary DXF, the whole drawing in one file, and a file without its units give no model. The settings above follow from that; the DXFOUT options are quoted from BricsCAD's help.

B0 · From the drawings as drawn to the marked set

No export from your drafter yet? The reference pack's sheets/ folder holds the nine sheets exactly as B00 writes them; start B0 from those.

The nine sheets as drawn carry no settings: the Modeller cannot tell which CAD layer is a column, how deep the footings go, or where the expansion joint is. In this step you tell it, in the Drawing metadata panel, and save the result as nine …_marked.dxf copies. Every value below is read from the drawings (the source is named in each row); nothing is invented. Type the numbers exactly as written.

The panel has sections you open by clicking their title: All defaults (the yellow list), Sheets (one card per sheet), Layers, Body heights, Exclude areas. The badge at the top says Blocked · n (n things still missing) or Qualifies.

# Do Confirm on screen Result
B0.1 Open the Modeller. 📂 Open → Open 2D drawings (.dxf)… and select all nine sheets exported in B00: 0_FLOOR_PLAN.dxf, 3_BEAM_LAYOUT.dxf, 4_FOUNDATION_LAYOUT.dxf, 1N_ELEV_NORTH.dxf, 1S_ELEV_SOUTH.dxf, 2_ELEV_WEST.dxf, 7_ELEV_EAST.dxf, 8_SECTION_AA_TRUSS.dxf, 5_DETAILS.dxf The Drawing metadata panel opens. The badge reads Blocked with a number (58 or 99 on the two exports this guide was proven on: the number depends on how the sheets were cut and is not a check). All defaults lists 34 yellow rows: what the Modeller read from the files (units, sheet roles and names, grid lines) ☐ Pass ☐ Fail
B0.2 In All defaults, press Accept stated + read The list grows to 113 yellow rows: the grid lines, level lines and roles that follow from the first ones ☐ Pass ☐ Fail
B0.2b Press Accept all 0 yellow rows. The badge still reads Blocked with a smaller number (48 or 89). In Sheets, eight cards now show a role (3 PLAN, 4 ELEV, 1 SECTION); 5_DETAILS is the notes sheet ☐ Pass ☐ Fail
B0.3 In Sheets, open any card. In its Set field replace BUILD-NAME with SHED and press Enter Every sheet's Set reads SHED (typing it once fills all nine) ☐ Pass ☐ Fail
B0.4 Open Layers. Under each heading, pick the meaning of each CAD layer from its list, as in the table below. Where the table says one sheet only, press the small arrow at the right of the layer's row (Type this layer sheet by sheet) and pick the meaning on that sheet's line only After PLAN · Col = column the badge reads Blocked · 1; after ELEV · Wall = panel it reads Qualifies. When all ten are set, All defaults shows 14 yellow rows (sizes the Modeller assumes, such as the fan depth) ☐ Pass ☐ Fail
B0.4b In All defaults, press Accept all 0 yellow rows ☐ Pass ☐ Fail
B0.5 Open Body heights. It lists footing and beam as waiting (no elevation shows them). Type footing: z0 -1.4478, z1 -1.143, Add. Type beam: z0 3.098794, z1 3.352794, Add Two rows: @BODYZ=footing,-1.4478,-1.143 and @BODYZ=beam,3.098794,3.352794. The badge still reads Qualifies ☐ Pass ☐ Fail
B0.6 In Sheets, open each elevation and the section card in turn. Under Level datums (@Z), type the height 0.6096 in the first box and the card's y (table below) in y where drawn, then Add Each of the five cards lists a new @Z=0.6096 row beside the two it read itself (@Z=0 and the eave or ridge height). The badge still reads Qualifies ☐ Pass ☐ Fail
B0.7 Open Exclude areas. Choose 3_BEAM_LAYOUT in its list and press Exclude area (the button now reads Drag a box). On the canvas, zoom to the bay between grid 06 and grid 35: the beam layout's expansion joint is the pair of close vertical lines (about 22 cm apart) running across all four rows A to D. Drag a box from above row A to below row D that holds both lines and the small break marks beside them: start about half a metre left of the left line (not more than 1 m: two short beam ends start 1.05 m to the left) and stop about 25 cm right of the right line. The break marks reach 18 cm out from the lines; the beams of the right-hand block start 37 cm right of the right line, so the box must stop before them. Press Drag a box again to leave the tool Exclude areas lists one row, 3_BEAM_LAYOUT @EXCLUDE=… with the box's four numbers. Without it the joint's two lines are read as four extra beams (B2b would then read 515 elements, not 511) ☐ Pass ☐ Fail
B0.8 Read the top of the panel The badge reads Qualifies; All defaults has 0 yellow rows ☐ Pass ☐ Fail
B0.9 Press Save marked copies (at the foot of the panel) Your browser downloads nine files named 0_FLOOR_PLAN_marked.dxf … 5_DETAILS_marked.dxf, the names used from B1 on. The panel says Downloaded: …; the files you opened are unchanged ☐ Pass ☐ Fail

B0.4 · the ten layer meanings

Heading in Layers CAD layer Pick Where it is read from
PLAN sheets Col column the 12"×12" column squares on the plans
PLAN sheets Fo footing the F-1 footing outlines on the foundation layout
PLAN sheets Dim beam, 3_BEAM_LAYOUT only (one sheet only) the B-1 / B-2 beam lines of the beam layout (on the other plans the layer is left unread)
PLAN sheets Rod doorswing the door arcs of the floor plan (Rod is on the floor plan only, so its row has no arrow)
ELEV sheets Wall panel the brick-wall hatches of the gable ends
ELEV sheets Rod fan the exhaust fans drawn on the elevations
ELEV sheets Dim net the zigzag nets above the low bays
ELEV sheets Win door the meaning the supplied set carries; it changes no element count in this test
ELEV sheets 0 column, 1S_ELEV_SOUTH only (one sheet only) the columns drawn on the south elevation
SECTION sheets Fo bar the truss members of section A-A

B0.6 · the five level datums (0.6096 m = 24 in, the plinth level PL: on every elevation the PL line is drawn 24 in above the ground line)

Card y where drawn
1S_ELEV_SOUTH -4446.6
1N_ELEV_NORTH -3895.2
2_ELEV_WEST -4515.7264
7_ELEV_EAST -3766.442
8_SECTION_AA_TRUSS -3726.416

B0.5 · where the body heights come from. Footing F-1 is 12 in thick, its top 45 in below the finished ground (z −1.143 m to −1.4478 m). The beams run from 122 in to 132 in above the ground (3.0988 m to 3.3528 m), as the section's lines give them; the elevations draw the beam soffit at 120 in, a 2 in difference the drawings leave open and this test does not settle.

Proven (witness W-UAT-B0, 2026-11-15): these steps, done in the real Modeller on the nine sheets as drawn, reach Qualifies, save nine copies equal mark for mark to the supplied …_marked.dxf set, and B2b's Convert then reads the same Converted: 511 elements (0 door/window fills), 2 openings cut. The datum y values are typed, not picked with the Pick button; picking was not part of the proof.

B1 · Get to know the drawings: one sheet at a time

Open the Modeller. The drawings are opened from 📂 Open → Open 2D drawings (.dxf)…

Where to click: Open, then Open 2D drawings (.dxf)

Picture B1-a · Modeller: Open ▸ Open 2D drawings (.dxf)

# Do Confirm on screen Result
B1.1 📂 Open → Open 2D drawings (.dxf)… and select only 0_FLOOR_PLAN_marked.dxf The Shed floor plan is drawn on the canvas, as in picture B1-b: the long rectangle of the shed with its grid lines and column marks. The badge in the Drawing metadata panel reads Blocked for one sheet on its own: that is expected, one sheet is not yet a building ☐ Pass ☐ Fail
B1.2 Fold the 2D Drawings panel away (the fold button in its title bar) and close the Drawing metadata panel (✕) to see the whole drawing. Turn the mouse wheel to zoom, drag to move You recognise your own floor plan ☐ Pass ☐ Fail

Shed floor plan on its own

Picture B1-b · Shed · Floor plan · sheet 0_FLOOR_PLAN.dxf, on its own

# Do Confirm on screen Result
B1.3 Reload the page. Open only 3_BEAM_LAYOUT_marked.dxf The beam layout is drawn, as in picture B1-c ☐ Pass ☐ Fail
B1.4 Reload the page. Open only 4_FOUNDATION_LAYOUT_marked.dxf The foundation layout is drawn, as in picture B1-d ☐ Pass ☐ Fail

Shed beam layout on its own

Picture B1-c · Shed · Beam layout · sheet 3_BEAM_LAYOUT.dxf, on its own

Shed foundation layout on its own

Picture B1-d · Shed · Foundation layout · sheet 4_FOUNDATION_LAYOUT.dxf, on its own

An elevation or the section opened on its own shows nothing: it has to stand on a plan. You will see them in the next step, standing in place.

B2 · Open all nine sheets: the drawings arrange themselves

# Do Confirm on screen Result
B2.1 Reload the page. 📂 Open → Open 2D drawings (.dxf)… and select all nine …_marked.dxf files at once The 2D Drawings panel is titled 9 SHEETS and lists each file with its role: three PLAN rows, four ELEV rows, the section and the NOTES sheet (picture B2-a) ☐ Pass ☐ Fail
B2.2 Read the top of the Drawing metadata panel The green badge reads Qualifies. Under it a line reads MISSING SHEETS · no list … INCONCLUSIVE: that is expected, because these nine files carry no list of the sheets a set should have, so the Modeller cannot count missing ones; it does not stop Convert. The SHEETS list shows each sheet with its role: three PLAN, four ELEV, one SECTION, one NOTES ☐ Pass ☐ Fail
B2.2b Below the sheets, find the yellow block ALL DEFAULTS. It says 14 yellow in 1 group. Click the ▸ on the group to open it and read the 14 rows. Each row is one setting the Modeller applied because the drawings do not state it: its name and value (for example building.type = General, fan.blades = 4, bodies.pair_max_width = 0.5), then a sentence saying what it does. These rows are conventions, so clicking one does not jump to a place on the sheet. To see a whole sheet with its markings drawn on it, press Sheet on a sheet’s card; Esc (or the ✕) closes it again You have read all 14 rows and agree with each value for your shed. Ten rows end in [guess], the Modeller’s assumptions: building.type, column.top_under_beam, fan.blades, fan.depth, fan.housing_wall, net.thickness, panel.plane, profile.angle_heel, profile.angle_mesh and section.spacing. Read those hardest. Write any value you do not accept on the Notes line. Source: each row’s own sentence says where the value comes from ☐ Pass ☐ Fail
B2.2c Do nothing to the yellow rows yet: Convert (B2.6) works with the 14 rows still open. Optional: press Accept all (the button above the group; no key is needed) to mark them as yours. To keep just one, press ✓ Keep this value at the right of its row The panel itself says the defaults stay applied and Convert is not held up by them. Keep this value on a row removes that row and no other (14 becomes 13). Accept all takes the yellow count from 14 to 0 and the block empties. Either way the badge stays Qualifies and Convert gives the same result (B2.6). If your browser still shows 3 rows left after Accept all, it is running an older copy of the Modeller: reload the page (Ctrl+F5) ☐ Pass ☐ Fail
B2.3 These nine sheets carry every value, so they open already in place: the Modeller does not replay anything on opening. Press Arrange in the panel to watch them move into place The status line counts Step 1/46 … Step 46/46 (one step per setting, the last is @CUT). The plans lie on the ground; each elevation stands on the side it shows; the section stands across the shed (picture B2-b). The details sheet is not placed (it is notes only) ☐ Pass ☐ Fail
B2.4 Fold the 2D Drawings panel away, close the Drawing metadata panel (✕), and orbit with the mouse You can see the floor plan you looked at in B1 lying flat, with the four elevations standing around it ☐ Pass ☐ Fail

The nine Shed sheets opened: the 2D Drawings panel and the Drawing metadata panel

Picture B2-a · Shed · all nine sheets opened: the list of sheets with their roles, and the verdict Qualifies**

The nine Shed sheets arranged in place

Picture B2-b · Shed · the nine 2D sheets arranged in place: plans flat, elevations and section standing

The arranged Shed sheets seen from above

Picture B2-c · Shed · the arranged sheets seen from above: the floor plan again, now with the other sheets around it

B2b · Convert the drawings to the 3D Shed

# Do Confirm on screen Result
B2.5 If you pressed Arrange, wait until the status line stops counting Step n/46 (or press Esc to stop it). Unfold the 2D Drawings panel and tick Complete the building (floor slab, roof) The box is ticked ☐ Pass ☐ Fail
B2.6 Press Convert (ringed in picture B2-d) Before you press it, the panel’s status line reads Structure set: 445 bodies will be built, 4 left out (listed as advisory: no elevation or conflicting heights). After it: Converted: 511 elements (0 door/window fills), 2 openings cut. The Shed is built in 3D: columns, walls, beams, the roof on its trusses, doors and fans (picture B2-e). The yellow count is unchanged by Convert ☐ Pass ☐ Fail
B2.7 Orbit around the model It is the shed as these sheets draw it: one row of columns on each grid line of the floor plan (14 lines along the length, 4 across) ☐ Pass ☐ Fail
B2.8 Export → Viewer database (.db) (ringed in picture B2-f) A .db file is downloaded ☐ Pass ☐ Fail
B2.9 Open the front door, Buildings / IFC, then the card Blank Viewer · Open your own .db file. In the blank Viewer press Ctrl+O (Open Building) and choose the .db The status line reads DONE — SHED 511 elements, the same count as the Convert; orbit with the mouse ☐ Pass ☐ Fail

Tick Complete, then press Convert

Picture B2-d · Shed · tick Complete, then press Convert, in the 2D Drawings panel

The Shed converted to a 3D model

Picture B2-e · Shed · converted to a 3D model (511 parts when these pictures were taken)

Export, Viewer database

Picture B2-f · Modeller: Export ▸ Viewer database (.db)

Full detail of every panel: DXF2BIM guide.

B3 · Fit the 4D schedule and the 5D rates to your local scene

The schedule and the cost come from reference files the Viewer ships with. You edit your own copy in the browser. Full detail: Your own 4D / 5D references.

Reference Open it from Example edit for this test
5D Rate Pack (the active pack, for example cidb2024_my) Settings → Edit Project JSON → 5D Rate Pack raise the rate of one material (for example walls) by 10 %
4D Schedule Template Settings → Edit Project JSON → 4D Schedule Template add waiting days after one phase: in dependencies → within_level, raise lag_days of the superstructure rows by 5. (A phase has no length of its own to type: its length is worked out from the parts and the crews)
4D Sequence & Labour Rules Settings → Edit Project JSON → 4D Sequence & Labour Rules change one trade’s crew size
# Do Confirm on screen Result
B3.1 Note the Viewer’s total cost (Find panel: total cost; it is the cost of the 13 drawn bays, see the note at the top of chapter B) and the schedule’s finish date (Time Machine, key T) With the shipped rates the total reads USD 355,097.98 (RM 1,365,761) — total building cost (the digits may be grouped differently in your browser's language). The amount in brackets is the rate pack's second currency (RM), whatever language you choose; your local currency for the chosen language is in development. A higher figure, such as USD 358,943.48, means the B0.7 exclude box missed the expansion joint. Write the total and the finish date down: _ / _ ☐ Pass ☐ Fail
B3.2 Make the rate edit and the lag edit above. Your copy is saved in this browser as you type The form keeps your value; a list shown as JSON text must stay valid JSON ☐ Pass ☐ Fail
B3.3 Reload the Viewer tab, so it reads your copies The building opens again ☐ Pass ☐ Fail
B3.4 Read the total cost again It moved in the direction of your rate edit ☐ Pass ☐ Fail
B3.5 Open Time Machine (key T). Press Jump to start, then Build The finish date moved by the days you added (5 on each edited row); the day counter and the placed count rise as the parts go up in order ☐ Pass ☐ Fail
B3.6 ⬇ Download your edited files, then Reset them You keep your copies as files; the Viewer is back on the shipped references ☐ Pass ☐ Fail

The Inspect drawer: Measure, Clash, X-Ray, Section, Time Machine, 4D / 5D

B4 · Send the model to the ERP as a Project Order

Do this in the Viewer, on the Shed you opened in B2.9. (In the Modeller, ERP ▸ Project Order prices a building that was opened from a database; for a model made from drawings it tells you to use this route.) Full detail: Send it to ERP.

# Do Confirm on screen Result
B4.1 Click the model, press F (the Find panel). Its list opens by storey: click Level 1 (511), the whole Shed (the two parts under Unknown are openings, priced 0) The bar reads Level 1 · 1 storey USD 355,097.98 (B3.1's total) and shows the button › ERP. For a moment the amount shows every decimal, then the cents ☐ Pass ☐ Fail
B4.2 Press › ERP The status line reads Project Order: 11 lines · contract USD 355,098 (saved) (12 lines if Time Machine has built the schedule in this tab: the order then follows its tasks; the amount is the same) and a link SHED #… ↗ appears (the number is the Project Order's id, e.g. SHED #990001). If you did B4 before in this browser, the link shows already at B4.1 and › ERP first asks Push again? (B4.3): press Push again ☐ Pass ☐ Fail
B4.3 Press › ERP again, then Push again in the box First a box Push again? reads SHED #… is already a Project Order. A second push adds only what is not there yet. (buttons Cancel and Push again; Cancel or Esc pushes nothing). After Push again: Project Order: 0 lines: nothing new is added, the order is keyed by the model's name (SHED) ☐ Pass ☐ Fail
B4.4 Click SHED #… ↗. On the Kernel ERP sign-in page choose GardenAdmin, then Log In The ERP opens on the project SHED (BIM: SHED) with its planned amount, 355097.97658 (B4.1's total, every decimal). Its Phase tab holds 6 phases (1 of 6; 5 if the schedule was built), the first Substructure 1,023.22458. A phase's Task tab holds its tasks (Substructure: one, CONCRETE_GANG), and Task Line the model's lines with the same planned amount (Substructure: one line, 1,023.22458): a line shows in the tab of its lowest level, as in iDempiere (Task Line: a task is set; Phase Line: a phase but no task; Project Line: neither), so Project Line and Phase Line read 0 records ☐ Pass ☐ Fail

If your ERP is a legacy iDempiere (not the Kernel ERP; the pilot client's case): your administrator installs the BIM OOTB plugin in it once (A5). Then do B4 in the Viewer that your iDempiere serves. The steps are the same; only where the Viewer comes from and what you confirm change. (Why: a browser does not let a page from another site call your iDempiere, so the Viewer is served by the iDempiere itself.) Do L1 to L3 before chapter C: the project SHED that L2 creates is the Shed in your iDempiere, and chapter D's figures include it.

# Do Confirm on screen Result
L1 Open your iDempiere/bimootb/viewer/viewer.html?blank=1&erpUser=GardenAdmin&erpClient=11&erpRole=102&erpOrg=11&erpWarehouse=103 (GardenWorld's user and ids; use your own), press Ctrl+O and open the Shed's .db as in B2.9 The Viewer opens the Shed: DONE — SHED 511 elements ☐ Pass ☐ Fail
L2 Do B4.1 (Level 1, the whole Shed), press › ERP, type your iDempiere password in the window Sign in to iDempiere, and press Push The window shows your user and ids, filled in. Then the status line reads iDempiere Project #… · created {"categories":3,"products":11,"projects":1,"phases":6,"tasks":8,"lines":11,"uoms":1} (the first push into your iDempiere also creates the Shed's product categories, products and unit) and the link SHED #… ↗ appears, with the same number (before the push there is no link). If you press › ERP again, the box Push again? asks first; a second push creates nothing ("projects":0, all 0). (Chrome may show its own password windows: press OK, then No thanks) ☐ Pass ☐ Fail
L3 Click SHED #… ↗ and log in to your iDempiere (tick Select Role, choose HQ, as in chapter C; Chrome may show its own windows: press OK, then No thanks) The Project window opens on SHED (BIM: SHED) with Planned Amount 355,097.97658 (B4.1's total, every decimal) ☐ Pass ☐ Fail

B5 · Mark your run against the reference pack

This is the step that How do I pass? (at the start of this guide) points to. The UAT Run Checker compares what your run produced with the run this guide was proven on, stage by stage. It reads your files in your browser; nothing is uploaded. Keep the files from B0.9 and B2.8 and the two lines from B2.9 and B3.1 for this step.

# Do Confirm on screen Result
B5.1 Download the reference pack (link in What you need) and open the UAT Run Checker. In box 1 choose the pack's .zip Under box 1: Pack intact: 19 files checked, built 2026-11-22 …. A damaged or wrong file is refused, and Mark my run stays off ☐ Pass ☐ Fail
B5.2 In box 2 select your nine …_marked.dxf from B0.9 (all at once); in box 3 your SHED_extracted.db from B2.8; in box 4 paste the Viewer's status line from B2.9; in box 5 the total-cost line from B3.1 (before your rate edit) The boxes hold your files and lines ☐ Pass ☐ Fail
B5.3 Press Mark my run One row per stage: B0.9 marked sheets, B2.8 Viewer database, B2.9 status line, B3.1 total cost, each PASS, FAIL or NOT GIVEN, with the reason under it. Your run reads PASS when all four pass. A tester who skipped B00 and B0 has no marked files: B0.9 reads NOT GIVEN and the run PARTIAL PASS ☐ Pass ☐ Fail
B5.4 Press Download result (uat_result.json) and attach the file to this sign-off The file is saved ☐ Pass ☐ Fail

Proven (witness W-UAT-CHECK, 2026-11-22, the one-cost pack) on the pack as it is served: a run equal to the proven one marks PASS on all four rows; a run whose B0.7 exclude box was skipped marks FAIL on all four (515 elements, USD 358,943.48); an empty form marks INCONCLUSIVE; a pack with one file changed is refused.

Notes (chapter B): __________


C · ERP: the hands-on exercise (Project Mgmt Accounting, as GardenWorld Admin)

Use the 12 test projects. The table says, per project, what to make. The products are the Construction products of A3.6 (not GardenWorld's own); use any GardenWorld vendor, the Purchase price list and HQ Warehouse. Do not type a price: the order line takes it from the price list, which is the product's standard cost rounded to the cent (68.1167 becomes 68.12). On each document, set Project to the test project (the windows do not ask for a phase).

Log in for chapter C: log in as GardenAdmin (password GardenAdmin on a fresh GardenWorld), tick Select Role, and choose the organization HQ and the warehouse HQ Warehouse (with the default * an order will not save: Fill mandatory fields: Organization, Warehouse). If Chrome shows Change your password, press OK; if it asks Save password?, press No thanks (else it takes the keys meant for the page). Each document opens its own window tab: close it (×) when done, or the first tabs are pushed off the strip.

Product Name Unit Standard cost (USD)
PWD-04.2 Brick masonry M3 68.1167
PWD-07.2.2 RC 1:2:4 column M3 115.5250
PWD-08.1.2 Reinforcement bar Grade 400 KG 0.8333
PWD-10.6 Steel section KG 1.0750
PWD-10.21 Profiled metal roofing M2 4.8167
Project Name Phases ticked (from the pack) Purchase orders How far the completed order goes Issue to the project
TD_RIVERSIDE Riverside Tower 3 of 5 complete: 29 M3 PWD-04.2; leave in Draft: 7 M3 PWD-04.2 Paid in full 3 M3 PWD-04.2
TD_DEPOT North Depot 1 of 4 leave in Draft: 1,008 KG PWD-08.1.2 — 92 KG PWD-08.1.2
TD_BRIDGE Bridge Deck 2 of 4 complete: 21 M3 PWD-07.2.2; leave in Draft: 31 M3 PWD-07.2.2 Half paid 5 M3 PWD-07.2.2
TD_CLINIC Clinic Wing 2 of 4 — — 107 KG PWD-10.6
TD_DATAHALL Data Hall 1 of 3 complete: 1,674 KG PWD-10.6; leave in Draft: 1,116 KG PWD-10.6 Received 178 KG PWD-10.6
TD_SUBSTATION Substation 1 of 3 complete: 104 M2 PWD-10.21 Ordered only —
TD_CARPARK Car Park 2 of 3 — — 95 M2 PWD-10.21
TD_SCHOOL School Block 3 of 4 complete: 1,350 KG PWD-08.1.2 Paid in full 321 KG PWD-08.1.2
TD_PUMP Pump Station 1 of 3 — — 36 KG PWD-10.6
TD_OFFICE Office Fit-out 0 of 3 — — —
TD_WAREHOUSE Warehouse 3 0 of 3 leave in Draft: 133 M2 PWD-10.21 — —
TD_PLAZA Plaza 3 of 3 — — 110 KG PWD-08.1.2

The products cost at Standard: a receipt at any price leaves a product's cost where it is, and every issue raises the project's Spent by quantity × standard cost. With this table the projects spread across the dashboard's Budget colours (chapter D) instead of all turning red. Five projects (TD_DEPOT, TD_CLINIC, TD_CARPARK, TD_PUMP, TD_PLAZA) issue a product that was never received, so its on-hand quantity goes negative. GardenWorld allows that; a warehouse that does not allow negative stock refuses those issues.

C1 · Purchase orders

Make one order per row of the table that has a purchase order, with the quantity it states.

# Do Confirm on screen Result
C1.1 Purchase Order window, New. Header: Business Partner Seed Farm Inc. (or any vendor), Price List Purchase, Warehouse HQ Warehouse, Project the test project (the field sits in the header). Save. Tab PO Line, New: Product the table's product, Quantity from the table; leave the price as the price list gives it. Save The line price is the product's standard cost rounded to the cent, as the Purchase list prices it (for example 68.12 for PWD-04.2, standard cost 68.1167). The order's Total Lines = quantity × that price (for example 29 × 68.12 = 1,975.48) and Grand Total is the same (the tax rate is 0). Source: the price is the product’s Price tab, Purchase list (A4.2); multiply it by the quantity yourself ☐ Pass ☐ Fail
C1.2 Document Action ▸ Complete ▸ OK on the orders the table marks complete; leave the others as they are Document status Completed on those, Drafted on the others ☐ Pass ☐ Fail

C2 · Material receipt

# Do Confirm on screen Result
C2.1 For each completed order whose How far is Received, Half paid or Paid in full: Material Receipt window, New. Header: Business Partner the same vendor, Order the purchase order (the project fills in from it). Save. Tab Receipt Line, New, choose the Order Line (product, quantity and Default HQ Locator fill in). Save, then back on the header Document Action ▸ Complete ▸ OK. (Do not use Create lines from: on this iDempiere build it lists no lines.) The receipt is Completed and carries the order's product and quantity. The product’s on-hand quantity rose (menu entry Storage per Product: type the name in the menu’s Search box), and in the Product window, tab Costs, its Standard cost did not change ☐ Pass ☐ Fail

C3 · Vendor invoice and payment

Only Half paid and Paid in full orders (TD_BRIDGE, TD_RIVERSIDE, TD_SCHOOL).

# Do Confirm on screen Result
C3.1 Purchase Invoice and Credit/Debit Note window, New. Header: Target Document Type AP Invoice, Business Partner the same vendor, Project the test project. Save. Then press Create lines from, choose the purchase order (or its receipt), tick the line, and press the Create lines from button of the window that opened (not the header's; the line is saved with it). Then Document Action ▸ Complete ▸ OK The invoice is Completed; its Grand Total equals the order's ☐ Pass ☐ Fail
C3.2 Payment and Receipt window, New. Document Type AP Payment, Business Partner the same vendor (this window finds a partner by its search key, not its name: type SeedFarm, the vendor's search key in the Business Partner window, A4.1; its search opens with Vendor = No: set Vendor to Yes, press ReQuery, choose SeedFarm), Invoice the invoice you just made (the amount fills in; the Project field disappears once an invoice is chosen, that is normal), Bank Account MoneyBank 1234, Tender type Check. For Half paid change Payment amount to half the invoice total, rounded up to the cent (TD_BRIDGE 2,426.13: pay 1,213.07, and 1,213.06 stays open). Save, then Document Action ▸ Complete ▸ OK The payment is Completed. On the invoice, Paid is ticked for Paid in full; for Half paid it is not, and the open amount is the other half ☐ Pass ☐ Fail

C4 · Issue materials to site

This is done in two parts, once per test project that has an issue in the table (nine projects). The pack's projects are category General, and iDempiere refuses to issue material to a General project (Project not Work Order or Asset), so each project is first set to the Work Order (Job) type.

# Do Confirm on screen Result
C4.1 Project window, open the test project. Press Set Project Type, choose Work Order (Job), OK. Then in the header set Line Level to Phase and Save (the test projects carry Project, which hides the Phase tab) The message says OK. The project's phases are still there (the Phase tab still lists them) and the Set Project Type button no longer accepts another type ☐ Pass ☐ Fail
C4.2 Menu Project Management ▸ Issue to Project. Project the test project, Locator Default HQ Locator, Product the table's product, Movement Quantity from the last column, Movement Date today. Leave Shipment/Receipt, Expense Report and Project Line empty. OK. Close the Issue tab when done (each issue opens its own tab) The message says Created 1 ☐ Pass ☐ Fail
C4.3 Project (Lines/Issues) window, find the project, tab Issues One issue line with the product and quantity, Document Status Completed ☐ Pass ☐ Fail
C4.4 Back in the Project window, look at Project Balance in the header It rose by quantity × standard cost: TD_RIVERSIDE 3 × 68.1167 = 204.35, TD_BRIDGE 5 × 115.525 = 577.63, TD_DATAHALL 178 × 1.075 = 191.35 (the window shows 4 decimals, for example 204.3501 and 577.625: pass on the rounded figure). A project that issues nothing stays at 0 Source: the quantity is on the issue line (C4.3) and the cost is the product’s Standard cost on its Costs tab; multiply them yourself and compare with Project Balance ☐ Pass ☐ Fail

C5 · Tick a phase

# Do Confirm on screen Result
C5.1 Project window, a test project (for example TD_DEPOT), tab Phase (no Phase tab: the project did not go through C4.1, so first set Line Level to Phase in the header and Save). Open the next phase that is not ticked (in the list: click its name, then its pencil Edit Record; if the tab shows one phase as a form: Next record). Set Invoice Rule to None (the project's own rule; without it Save is refused: Fill mandatory fields: Invoice Rule), tick Complete, Save The phase stays ticked (for TD_DEPOT 2 of 4 now); that project's Done on the dashboard rises (chapter D) ☐ Pass ☐ Fail

Notes (chapter C): __________


D · The dashboard (Project Mgmt Accounting; the read job: System Setup)

The dashboard reads a file that a small read job writes from your iDempiere. Run the job first, and again whenever you want fresh figures (it needs Node.js; on a server that is not localhost it also needs BRIDGE_USER and BRIDGE_PASS, else it stops: the full line with user, password, tenant and role is in the Developer's note):

BRIDGE_BASE=http://<your-idempiere>:<port> node capex/tools/legacy_snapshot.js

It writes the file capex/legacy_snapshot.json inside your copy of the repository (the folder from A1.1, next to index.html), prints a line §DASH_LEGACY_SNAPSHOT … projects=15 … unavailable=[] (14 on a fresh GardenWorld, plus SHED from L2), and ends with a line §DASH_LEGACY_READ_VERDICT PASS …. Then open /capex/index.html?source=legacy on the server that holds that copy (see How the dashboard connects to the data). Every tile is described in The dashboard page. Without SHED (you did B4 only in the Kernel ERP, or skipped L1 to L3), your iDempiere holds 14 projects and the rows below read 14 and 14, USD 4,667.80, Within 7 / Over 2 / Not started 5, 43 % of plan, and on Home CAPEX Total Projects 14 and CAPEX Approved Budget 4,668.

The dashboard

# Do Confirm on screen Result
D1 Read Total Projects and Active Projects 15 and 15: the 12 test projects, GardenWorld's own Standard and Landscape, and SHED from L2 (plus any of your own). Step into the source: click the number: the side panel lists the projects behind it, and its row count is the figure. ƒ formula under the tile shows the measure (D7) ☐ Pass ☐ Fail
D2 Read Approved Budget The sum of the planned amounts, per currency: USD 359,765.78 (the 12 test projects 4,067.80, Landscape 600.00 and SHED 355,097.98). Step into the source: click the number; add the Approved column of the panel yourself. Press ERP ↗ on a project (it opens your iDempiere: log in if it asks): iDempiere’s Project window shows the same figure in Planned Amount, and it equals the sum of Planned Amount on the Phase tab ☐ Pass ☐ Fail
D2b Read the Budget tile (Within / Over / Not started) Over lists TD_CARPARK (Spent 457.59 against a plan of 330.00) and TD_DATAHALL (191.35 against 181.50), the other 7 projects with issues are Within; Not started is 6: TD_OFFICE, TD_SUBSTATION, TD_WAREHOUSE, GardenWorld’s own Landscape and Standard, which carry no spending on a fresh GardenWorld, and SHED (nothing issued to it yet). The three counts read Within 7, Over 2, Not started 6. If your server's Standard project already carries spending, it moves out of Not started Step into the source: click Total Projects and read each project’s Spent, Approved and Budget columns: Over is Spent above Approved, Not started is Spent 0 ☐ Pass ☐ Fail
D3 Read Actual Cost (Spent) It rose by what you issued in C4: 2,020.45 over the 12 test projects. GardenWorld’s own projects carry no spending on a fresh GardenWorld, so the tile reads USD 2,020.45, 1 % of plan (SHED's 355,097.98 is in the plan) (add whatever your own projects already carry). Step into the source: click the number and add the Spent column (it adds up to 2,020.46, as each row is rounded to the cent: pass at the tile's 2,020.45); each project’s Spent is Project Balance in iDempiere’s Project window (C4.4) ☐ Pass ☐ Fail
D4 Open Procurement Risks in the left menu. Then open a test project's page (D5) and its Procurement tab Left menu: Open purchase orders = the 5 you left Drafted, USD 6,741.25 in total (each order line is priced to the cent, C1.1). Project page: the Supply chain card shows that project's order at the stage you took it to (TD_SUBSTATION Ordered, TD_DATAHALL Received, TD_BRIDGE Invoiced, TD_RIVERSIDE and TD_SCHOOL Paid) and lists its receipt, invoice and payment Step into the source: each document number in the Supply chain card is a record number: open that receipt, invoice or payment in iDempiere (Material Receipt, Purchase Invoice and Credit/Debit Note, Payment and Receipt) and read its status and amount ☐ Pass ☐ Fail
D5 Click a number on a tile The drill panel lists the projects behind it; click a project to open its page ☐ Pass ☐ Fail
D6 On the project page of TD_RIVERSIDE, open the tabs Overview: Approved 371.25, 5 phases. The Schedule tab draws the 5 phase bars with the pack’s dates, the first 3 Complete Source: the project’s Phase tab in iDempiere (Planned Amount, start and end dates, Complete); read them there and compare ☐ Pass ☐ Fail
D7 Open ƒ formula under a tile The formula is shown; it is the same Performance Analysis measure your iDempiere holds (A2.3) ☐ Pass ☐ Fail
D8 Change Layout (top bar) to Executive and Skin to Dark, then back to Classic and Light The look changes. Executive shows fewer, re-labelled tiles (Actual Cost becomes Spent so far) with the same figures (359,765.78 approved, 2,020.45 spent); Classic shows them all again ☐ Pass ☐ Fail
D9 Log Out of iDempiere, log in again (tick Select Role, choose HQ, as in chapter C) and read the Home tab. Home goals are recalculated only when they are older than 30 minutes (System Configurator name ZK_DASHBOARD_PERFORMANCE_REFRESH_INTERVAL, 1800000 ms). If you opened Home at A2.2 less than 30 minutes ago, the goals still show the counts from before the test data (for example CAPEX Total Projects 2): either wait, or open System Admin ▸ General Rules ▸ System Rules ▸ System Configurator, set that name's Configured Value to 60000, save, and log in again The CAPEX goals show the same counts as the dashboard tiles (for example CAPEX Total Projects 15, CAPEX Active Projects 15), money in your login’s currency rounded to the unit (CAPEX Approved Budget 359,766 for the tile's 359,765.78). A goal that has a target shows its percentage of that target, not the count. The targets are the ones A2 installs, the plan of the system the dashboard was built on (Actual Cost, Committed Cost, Invoiced: USD 39,971,166.17; Health Green, Schedule On Time, Budget Within: 9 active projects). So on the test data Actual Cost reads 0 % and Health Green 33 % (3 of 9, measured 2026-11-23: the colours drift with the calendar), not the tiles' share; that is expected. Your own targets are set in the Performance Goal window (Measure Target) ☐ Pass ☐ Fail

Notes (chapter D): __________


Known limits (do not fail a step on these)

  • Proposed figures. Forecast, Procurement Risks and Handover use definitions we proposed; they await your confirmation.
  • Postings in the Kernel ERP. Project issues complete but are not yet posted to the books in the browser-based Kernel ERP; in your iDempiere they post as usual.
  • Task dates. Task dates are kept by the BIM Document plugin; without it, the Schedule tab draws phases only.
  • Standard costing is a PostgreSQL iDempiere set-up. The products script, and the change of GardenWorld’s accounting schema to Standard costing, are not available in the browser-based Kernel ERP. Applying the script changes how all GardenWorld products are costed on that server, so apply it on a test copy, not on a live GardenWorld.
  • This pack in the Kernel ERP. Loading this test pack into the browser-based Kernel ERP (rather than into your iDempiere) is not available yet.

Sign-off

Chapter Role / name Date Passed / total Signature
A · Set up System Setup: / 17 (21 with A5)
B · BIM BIM: / 43 (29 if you were given the marked copies and skipped B00 and B0; +3 with L1–L3)
C · ERP Project Mgmt Accounting: / 10
D · Dashboard Project Mgmt Accounting: / 10