BIM → Project Order — Blueprint

Status: Tasks 0, A, C BUILT, witnessed & LIVE (browser-wired + deployed — bim-ootb PR #316: viewer/proj_fold.js?v=1 + erp/bim_orders_overlay.js?v=1; the › ERP button drives the fold). Re-witnessed 2026-06-15 against the deployed engine — §PROJ_FOLD plannedAmt=1055478 golden=1055478 match=true (6 phases · 9 tasks · 16 issued lines, idempotent, seqno traces to sequence_rules). §D/§E + §H/§I still PAPER. Sibling to docs/BIMtoERP.md. Built so far: §0/Task 0 substrate confirmed (W-PROJ-SCHEMA — canonical erp/ad_seed.db, 11 write targets, OPEN-3 resolved) · §A/Task A cost-on-selection + 5D-pack-in-Settings (W-FIND-COST) · §C/Task C the fold engine proj_fold.js (W-PROJ-PUSH/FOLD/SEQ — building selection → C_Project tree, idempotent, PlannedAmt == 5D golden via BigDecimal, seqno traces to sequence_rules; › ERP button wired). Remaining for §C: browser visual-drive + the cross-page hand-off so the ERP app reads the folded db (= BIMtoERP §B write-path). The one-line idea: the whole building (or any selected slice) becomes an iDempiere C_Project carrying its 4D schedule (phases/tasks) and 5D cost (planned BOQ lines), which iDempiere can then generate a Purchase Order from. Prime alignment: EXTRACT OR COMPILE ONLY. Phase/seq/dates come from the 4D template, price from the 5D template, qty from QTO. Never invent a phase, a date, a rate, or a line. Money/qty math via site/bigdecimal.js ONLY (see memory feedback_numbers_via_bigdecimal).

Noun vs verb. docs/BIMtoERP.md is the noun bridge — element Type→M_Product, GUID→A_Asset, on-hand (what a thing is in inventory). This doc is the verb bridge — the building as work to be done: project → phases → tasks → cost lines → PO. They share the IFC GUID join and the M_Product/M_Product_Category layer; the verb rides on the noun.

Executable lane: prompts/BIM_TO_PROJECT.md. ERP engine source-of-truth: build/erp/ (see docs/ERP.md). Round-trip plays through time_machine.js (the 4D Time Machine).


§0 — THE TWO TEMPLATES (the source of truth, both already exist)

The Project Order is folded from two editable JSON templates — nothing is invented:

Template Lives at Drives
4D sequence_rules.json viewer/rates/sequence_rules.json (LIVE, used by Time Machine injectGantt) ifc_class → {phase, sequence, resource} + labour productivity → phase structure, order, dates
5D 5D_rates.json / rate packs viewer/rates/<pack>.json (cidb-my, bcis-uk, rsmeans-us, …; loaded by rates.js) ifc_class → {rate, unit} → line price

Because the push reads the same sequence_rules.json that Time Machine already plays, the planned Project Order and the planned Time Machine are consistent by construction — and the "Actual" version (§D) measures variance against that one baseline.

Asymmetry to fix (carried from BIMtoERP point 4): the 4D sequence_rules.json is already editable via the Settings JSON editor; the 5D rate packs are not surfaced there. This lane adds a 5D rate-pack picker to Settings so the cost shown on a selection (§A) and the price pushed into a line (§C) use the same active pack — one source, no drift.


§A — THE GATEWAY: the Find panel selected bar

The Find panel (navigate_find.js) is the single gateway to the ERP side. Its #find-selected bar already carries the current selection + a ▶ Navigate button. It gains two siblings:

  • Check ERP (read) — the docs/BIMtoERP.md §A data-gated chip (product/asset/cost read).
  • > to ERP (write) — fold the current selection into a Project Order (§C).

Cost on the selected bar (precondition — surface, don't build). The compute already exists in nlp.js (calcCost(), getRate(), RATES, currency conversion — what powers "total cost"). The selected bar must show qty × rate for the current selection, in the active pack's currency, so the user sees the 5D number before pushing it. An honest gateway shows the cost it will commit.

Witness. - W-FIND-COST: §FIND_COST scope=<sel> elements=<n> qty=<q> cost=<bd> cur=<CUR> pack=<name> — cost folds exact == Σ(qty × rate) golden (BigDecimal); pack == active Settings pack.


§B — MULTI-SELECT (the enabler)

Today §NAV_FIND_002 gives multi-select for parent rows only (_selStoreys/_selDiscs, "plain = replace"). This lane extends the same Set model to type/category leaves (_selTypes/_selCats), so a user can tick several types/categories across the tree and push them as one Project Order slice. No new selection engine — extend the existing one; axis change still clears (the unify rule).

Witness. - W-FIND-MULTI: §FIND_MULTI axis=<a> picked=<ids> elements=<n> — selection set == union of ticked leaves; cleared on axis change.


§C — THE PUSH: selection scope → Project WBS (the isomorphism)

The Find panel's axes already ARE the project WBS levels. The granularity of the Project Order is just how deep you selected — no separate scoping UI:

Find selection Project Order level Key columns
nothing (whole building) C_Project (all phases) value,name,datecontract/datefinish,plannedamt,c_currency_id,m_pricelist_version_id
storey / discipline (parent row) C_ProjectPhase name(=4D phase),seqno(=4D sequence),startdate/enddate,plannedamt
type (leaf) C_ProjectLine plannedqty,plannedprice,plannedamt,m_product_id
category M_Product_Category grouping the lines m_product_category_id

Fold steps (idempotent, find-or-create, BigDecimal): 1. Header — find-or-create C_Project keyed on building value; span = 4D min/max dates. 2. Phases/tasks (4D) — for each phase in sequence_rules.json: C_ProjectPhase.name=phase, seqno=sequence; startdate/enddate from labour-productivity durations (the same dates Time Machine computes). Work packages by resourceC_ProjectTask. 3. Lines (5D) — each Type → C_ProjectLine: plannedqty from QTO, plannedprice from the active rate pack (rate × unit via site/bigdecimal.js), plannedamt=qty×price. m_product_id resolved by the same find-or-create as docs/BIMtoERP.md §B (M_Product.Value=Type); m_product_category_id from the Type's parent/category. 4. Roll-up — line→phase.plannedamt→project.plannedamt/plannedqty. 5. The Order — phases with a supplier c_bpartner_id: set generateorder → fold a C_Order PO (iDempiere's native Generate-PO-from-project). Gated: no supplier = plan-only project, no PO (non-invent). This is the literal "Project Order."

Witnesses. - W-PROJ-PUSH: §PROJ_PUSH project=<v> phases=+<np> tasks=+<nt> lines=+<nl> order=<co|-> — counts == selection; second run reports +0 (idempotent). - W-PROJ-FOLD: Σ project plannedamt folds exact == nD 5D golden (BigDecimal). - W-PROJ-SEQ: §PROJ_SEQ phase=<name> seqno=<n> start=<d> end=<d> — every phase name+seqno traces to a sequence_rules.json row; dates == Time Machine's planned dates for that phase.


§D — THE ROUND-TRIP: ProjectIssue → "Actual" 4D → split-screen Time Machine

Delivery against the order folds back into a second schedule version, so the viewer can play as-planned vs as-built.

  • Planned / Budget = today's generative timeline = kernel_ops ELEMENT_PLACE with estimated start/end (tagged version=planned). This is the 4D pushed as the Project Order.
  • Actual = a second timeline sourced from ERP delivery, not estimates: C_ProjectIssue.movementdate/movementqty (real, dated, docstatus-gated) + C_ProjectPhase.enddate/iscomplete → a second ELEMENT_PLACE set tagged version=actual.
  • The seam already exists: Time Machine distinguishes a generated from a captured schedule (_capActive; injectGantt() anchors onto a captured schedule). "Actual" is just another captured schedule whose source is ERP issues instead of an IFC schedule — no new render path.
  • Split-screen = two timelines (planned | actual) on one shared scrub cursor; divergence (actual lagging planned) = the schedule variance, painted red.
  • 5D variance rides the same event — the project already carries plannedamt vs committedamt vs invoicedamt. One C_ProjectIssue posting moves both 4D (actual schedule) and 5D (actual cost). One loop, two variances.

Two fences (the non-invent rules): 1. Versioningversion dimension on the schedule (planned|actual); never overwrite the planned baseline. 2. Issue→GUID allocation — a C_ProjectIssue is per-product, per-qty ("20 doors on date D"), not per-element-GUID. To paint actual progress on specific elements, allocate the issued qty back to GUIDs by the deterministic rule: light N of M elements of that Type within the issue's phase, ordered by seqno. You commit "20 doors done" honestly; you do not invent which individual door beyond the fixed seqno order. EXTRACT-only.

Witnesses. - W-PROJ-ACTUAL: §PROJ_ACTUAL phase=<name> planned_end=<d> actual_end=<d> var_days=<n> — actual dates trace to C_ProjectIssue.movementdate/phase enddate; never to estimates. - W-PROJ-ALLOC: §PROJ_ALLOC type=<T> issued=<q> lit=<n>/<m> order=seqno — lit count == issued qty (capped at M); the which is seqno-deterministic, re-run identical. - W-TM-SPLIT: planned + actual timelines render under one cursor; var_days == W-PROJ-ACTUAL.


§E — ROLLBACK: the history dots, scoped (no new UI)

Scrubbing a Project Order to redo BIM→ERP is not a bespoke button — it is the same ‹ dots › history gesture the user already knows from the viewer timeline and the ERP world-history "W", mounted scoped to the project. The pieces are shipped:

  • common/history_bar.js takes configure({mountHostId, source, treeKey}) → dock the bar inside the Project Order panel, source=doc, treeKey=this C_Project → its own timeline of dots.
  • crud_overlay.js exposes crudFoldBack / crudFoldForward ("REUSED UNCHANGED — no second history lane").

Behaviour: - Click back to the first dotcrudFoldBack walks every op back to before creation = the project is scrubbed; re-run > to ERP for a fresh push. - ForwardcrudFoldForward = redo to tip (scrub is itself reversible). - Committed-safe for free — folding back a committed doc goes through the status FSM (CO→DR via setDocStatus), not a delete; the §D "Actual"/variance data is protected with no special gating. The fold already does the right thing. - Deterministic redo — because the push reads only the two templates (§0), scrub-then-redo produces the identical Project Order (W-PROJ-PUSH second run = +0).

Standardization win: one bar, one mental model ("scrub the dots back to undo, forward to redo"), mounted everywhere — viewer, ERP, and now the Project Order panel. The user learns the gesture once; it works for BIM→ERP rollback too. This is why the history bar was extracted into a shared module.

Witness. - W-PROJ-ROLLBACK: §PROJ_ROLLBACK project=<v> dots=<n> foldback=<bool> rows_after=0 — first-dot fold-back leaves zero project rows; > to ERP re-push restores identical counts.


§F — What this is NOT (scope fences)

  • Not a live two-way ERP daemon — deterministic push + read against ERP.db, scrubbable via history.
  • Not invented financials/dates — price only from the active 5D pack, dates only from 4D durations, qty only from QTO, BigDecimal only.
  • Not a new geometry/render path — Project Order is a data fold; "Actual" rides the existing captured-schedule path in Time Machine.
  • 6D carbon / 8D safety ride-along is out of v1 — leave the seam (carbon = project attribute; hazards → C_ProjectIssue), fence it so it is not silently dropped.
  • Three Concerns stay split (BOM PRINCIPLE): WHAT = M_Product/M_Product_Category; HOW = UOM + rate pack + 4D sequence; WHERE = build/erp/ad_*.db.

§G — Build order (paper → code, when GO)

  1. Confirm build/erp/ad_full.db carries c_project* + c_order* (DONE — verified present); confirm canonical viewer-side ERP.db (shared with BIMtoERP OPEN-3).
  2. §A cost-on-selection (surface nlp.js compute on #find-selected) + 5D pack picker in Settings.
  3. §B leaf multi-select (_selTypes/_selCats).
  4. §C > to ERP push (find-or-create, idempotent) — header → phases (4D) → lines (5D) → PO.
  5. §E scoped history_bar mount (rollback) — verify crudFoldBack scrubs to zero.
  6. §D "Actual" schedule version + split-screen Time Machine (the round-trip). Each step lands with its witness §-line before the next. Whitebox §-log first; Playwright only drives/captures. ERP writes go to build/erp/ ONLY; never touch deploy/live/.

The §H lifecycle killers below are follow-on sub-lanes off this same plumbing (the GUID join, the signed fold, the two templates) — sequence them after §C–§E land.


§H — Lifecycle killers (follow-on sub-lanes, same plumbing)

Five high-value flows BIM users want, each reusing this lane's machinery and mostly already backed by existing code or seed tables (verified 2026-06-14). EXTRACT-only throughout: every amount traces to the rate pack / QTO / a real ERP row; BigDecimal only.

§H1 — Model-delta → signed Variation Order (highest value-per-effort)

The cost engine already exists: viewer/variation_order.js (S222) does FIDIC Clause 12 valuation + AACE change-order costing + EVM variance, ADDED ×1.0 / REMOVED ×0.3 / CHANGED ×1.3, schedule impact from the 4D productivity. Today it terminates in an Excel file. This sub-lane folds it into the ledger instead:

  • A model revision → GUID diff (added/removed/changed elements — the same elements_meta.guid join) → variation_order.js prices the delta → fold a signed C_Order amendment (or a C_Project variation line) in ERP, painted on the model, recorded in the history dots.
  • The VO is a reversible signed fold (crudFoldBack) — survives dispute, fully auditable.

Witness — W-PROJ-VO: §PROJ_VO rev=<r> added=<n> removed=<n> changed=<n> delta=<bd> co=<id> — delta folds exact == variation_order.js golden (BigDecimal); counts == the GUID diff.

§H2 — Progress claim / payment certificate (the get-paid side)

§C does the buy side (Generate-PO). This closes the cash-in loop: % complete per element/phase (from the §D Actual schedule) → certify → fold a C_Invoice/C_InvoiceLine progress billing (C_Project.projinvoicerule governs it; column present, set the rule value). Paint the model by claimed / certified / disputed.

Witness — W-PROJ-CLAIM: §PROJ_CLAIM phase=<name> pct=<%> claimed=<bd> certified=<bd> invoice=<id>claimed folds exact == Σ(lineplannedamt × pct) golden; ties to C_ProjectLine.invoicedamt.

§H3 — Owner handover: live as-built asset register + FM work orders (7D)

The seed already carries the full asset lifecycle: a_asset_addition, a_asset_delivery, a_asset_change, a_asset_retirement, a_asset_info_fin/_ins/_lic/_tax. On project completion (C_ProjectPhase.iscomplete), capitalize project lines into A_Asset with warranty / serial / O&M / insurance (reusing docs/BIMtoERP.md §B GUID→A_Asset). The owner taps an element → raises a maintenance request (R_Request). Deliverable: a queryable, live asset register bonded to the 3D model — not a 500-page handover PDF.

Witness — W-PROJ-HANDOVER: §PROJ_HANDOVER assets=+<na> warranties=<n> request=<id|-> — one A_Asset per completed-phase GUID; tap→R_Request traces to the element GUID.

§H4 — 4D lookahead procurement (just-in-time)

"What must I order this week to not slip?" The model already holds the dates: 4D need-dates (phase startdate minus lead time) + supplier lead times → fold M_Requisition/M_RequisitionLine (or POs) with required-by dates. Replaces the manual 6-week lookahead.

Witness — W-PROJ-LOOKAHEAD: §PROJ_LOOKAHEAD window=<6wk> items=<n> reqs=+<nr> — every requisition's required-by == phase startdate − leadtime; no item without a real need-date (non-invent).

§H5 — Embodied carbon as a parallel ledger (6D / ESG)

You already compute 6D carbon (templates/6D_carbon.json). Run it like cost: a carbon budget on the project, carbon actual folded per C_ProjectIssue (each delivery posts its embodied carbon the way it posts cost). Carbon budget vs actual, painted on the model. Regulatory tailwind; almost nobody integrates carbon at the transaction layer.

Witness — W-PROJ-CARBON: §PROJ_CARBON budget=<tco2e> actual=<tco2e> var=<tco2e> — actual folds exact == Σ(issued qty × carbon factor) golden; factors trace to 6D_carbon.json.

Sequencing: §H1 (VO) first — most reuse, loudest pain point. Then §H2 (claim) to close the cash loop, §H3 (handover) for the owner story, §H4/§H5 as differentiators. Each is a standalone sub-lane with its own witness; none blocks §C–§E.


§I — Reporting: Excel export the way QS/PM users actually want

Every §C/§H output gets an Excel report in the standard construction layout — not a raw dump. Reuse the existing engines, do not write a new Excel writer:

  • ERP-side reports (claim, VO register, cost/EVM, asset register) → the erp/ninja_excel.js engine: dictionary-driven, folds SQL over the tenant DB into a workbook and verifies every total by example to the cent. This is the right tool because its output is provably correct, not just formatted.
  • Viewer-side quick exports (BoQ, schedule) → viewer/excel.js (SheetJS/XLSX) + export_4d.js/export_5d.js, the same path variation_order.js already uses.
  • Match iDempiere print layouts where one exists → the erp/report_overlay.js foldPrint PrintFormat fold (already proven: Invoice 8/8, 48 cells, W-PRINTFORMAT to the cent).

The standard report set (the layouts users expect):

Report Grouping Columns (the conventional shape)
BoQ (Bill of Quantities) by trade / WBS phase Item · Description · Unit · Qty · Rate · Amount; section subtotals; grand total
Progress Claim / Payment Certificate by phase/line Contract value · Prev claimed · This claim % · This claim amt · Cumulative · Retention · Net
Variation Order register by VO VO no. · Description · Added/Removed/Changed · Cost impact · Schedule impact · Status
Cost / EVM report by phase PV · EV · AC · CV · SV · CPI · SPI
Schedule by phase (seqno) Phase · Start · End · Duration · % complete · Predecessor
Asset register (handover) by asset Tag/GUID · Product · Serial · Warranty · Value · Locator

Layout conventions (the "usually wants" details): - Title block atop each sheet: project name/value, report date, currency + rate-pack source (the non-invent traceability — the report says which pack/version priced it). - Frozen header row; grouped rows with section subtotals; bold totals row. - Number format: thousands separator + 2 dp; currency symbol from the active pack's meta.currency. - One workbook, multiple sheets when a flow spans reports (e.g. a project pack = BoQ + Schedule + Cost on three tabs) — mirrors the §C Export chooser's multi-select bundling. - Footer cites the source rows (GUID / C_* id) so any cell is traceable back to the model/ledger.

The hard rule (this project's ethos): verify-by-example to the cent. A report is not "done" because it is formatted — its totals must fold == the golden (ninja_excel.js already enforces this). A pretty workbook with a wrong subtotal is a failed report.

Witness — W-PROJ-REPORT: §PROJ_REPORT type=<boq|claim|vo|evm|sched|asset> rows=<n> total=<bd> golden=<bd> match=<bool> cur=<CUR> pack=<name>match=true (total == golden to the cent); currency + pack stamped in the title block; every section subtotal sums to the grand total.