CAPEX Dashboard โ€” Guide for iDempiere Users

โš  DEMONSTRATOR โ€” NOT OFFICIAL. Every screenshot and figure comes from a local GardenWorld test server (iDempiere 13) holding test projects, some of them repeat test runs. Treat every number as a sample (SAMPLE โ€” NOT OFFICIAL). The health and schedule rules are provisional until a client confirms them.

What this is. One set of project and capital-spending figures from your iDempiere, in three places:

  • The dashboard page: a full executive page in a browser. It reads your iDempiere and writes nothing back.
  • The Performance panel on your iDempiere Home tab: the same figures as ordinary Performance Goals, which you change in the stock windows.
  • The Performance panel on the twin's Home tab: the same goals in Kernel-ERP, the SQLite twin of iDempiere that runs in a browser.

What it changes on your iDempiere: no change to iDempiere's code or tables. The dashboard needs only read-only setup data. Sending a Project Order from a BIM model into iDempiere is a separate thing: that is one standard plugin.

Who reads what. Project manager: The dashboard page, The Home tab and What moves the numbers. Administrator: Changing it and Installing it. Everyone: Three places, What it does not do yet and Troubleshooting.


Three places, one set of figures

These are different screens over the same kind of rows. They are not one HTML page shown three times.

Dashboard page iDempiere Home tab Twin Home tab
What you see Seven tiles, five panels, project lists Performance dials, one per goal The same dials as iDempiere, on purpose
What defines the figures Formulas in code (capex/tiles.js) PA_Goal and PA_Measure rows The same rows
What calculates them The page, in the browser iDempiere The twin's goal engine, running the same SQL
Where its data comes from A file written by a small job Your iDempiere A copy of your iDempiere's rows, in the browser
Change a formula without code No Yes, in the stock windows Yes, in the same stock windows
Change the look without code No No No

Rich or editable: today you choose

A goal is one number on a dial, so the Home tabs cannot draw a stage pipeline, a Physical vs Spent panel or a project list. The page can, because it is not limited to what a goal expresses. But the page is the part you cannot change without a developer: its layout is in index.html and dash.css, and its formulas are in tiles.js. There is no editor for the page. On it you can only change the filters and the data source, and its tiles do not click through to records: the one link out is the BIM button.

The windows under Changing it edit a goal's numbers and SQL. They do not change how anything looks. Where a figure appears on both, the checks under How it was checked keep the two formulas in agreement.

What the twin does and does not add

The twin does not show more figures than iDempiere. It is built to show the same ones in the same way, and a difference is a defect to fix. What differs is where it runs:

The twin adds The twin lacks
Runs in a browser, with no server of its own The page's panels: Stage, Physical vs Spent and the lists are not on its Home either
The password stays with the job: the copy and the browser never hold it Six of its ten Home gadgets say Not ported yet, including Calendar, Views and Running Jobs
A Project Order folded from a BIM model can reach its Home before anything is pushed. A copy from iDempiere, while active, hides it until it is pushed Edits made in its windows stay in the twin: they do not reach your iDempiere
You can change a goal there without touching your server Nothing tells a user the copy is old. If the job stops, the figures just stop moving
Each saved edit is kept in a signed log Tested on a test server only, with a handful of projects

Inside its 30-minute refresh, one difference remains. The twin stores a recalculated goal on each device, so one user's Home does not refresh another's stored value. On iDempiere it does, because there is one database.

The twin's Performance panel: the stock goals, then the CAPEX goals, the same rows as iDempiere's

How close the page is to the design it follows

The page follows an executive dashboard a client prototyped. We have seen one screenshot of it, not its code or its formulas, so its tiles are matched by name.

The same: the title, the left menu's six items, the Org, Category and Status filters, Last Updated, the seven tiles and the five panels.

That design This page Why
Forecast Cost at Completion A figure definition pending No formula has been stated
Committed Cost Split into verified and contract Committed, with invoiced under it No column for that split has been stated
Project Stage The client's own five stages The Standard Phase names How those stages map to C_Phase is not agreed
Money One currency, in large units Each currency separately, in full Never added together
Explaining a tile An information mark The formula printed on the tile So anyone can check it in SQL
Tiles Icons and progress bars Plain text Not built
Data Described as live The last run of the job See Installing it

The figures themselves come from different data, so they will not match.


The dashboard page

Open the page with the sample data: real rows read from the test server, the date held at 4 Nov 2026 so it matches this guide.

The full dashboard page populated from the test server: seven summary tiles and five panels

How to read it

  1. Left menu. Dashboard is this view. The others are below. The red badge on Approval Pending is that count.
  2. Data source (bottom left). B ยท Legacy iDempiere is your server's data, from the job's file. A ยท SQLite ERP DB is the stock sample database shipped with the page: not your data, and not the twin's copy in your browser.
  3. Filters. Org, Category (ProjectCategory) and Status. Status starts on Active Projects. That changes the money tiles, as explained under Page and Home tab: why a figure can differ.
  4. Last Updated. The newest C_Project.Updated in the data, never the clock. An old date means old data.
  5. The ฦ’ line under each tile states its formula in iDempiere columns, so anyone can check it in SQL.

A tile with nothing to judge says no data, not 0%. A tile with no agreed formula says definition pending, not a guess.

The summary tiles

Money is shown per currency, never added together.

Tile Sample shows Where it comes from
Total Projects (All) 13, Closed: 1 Every C_Project. Closed = Processed = Y
Active Projects 9 IsActive = Y and Processed = N
Approved Budget USD 24,982,203.77, BDT 15,139,265.67 Sum of PlannedAmt
Actual Cost USD 342.59, BDT 7.97 Sum of ProjectBalanceAmt, also as % of plan
Committed Cost USD 1,347,462.62, BDT 1,000.00 (invoiced USD 8.10, BDT 0.00) Sum of CommittedAmt, with InvoicedAmt under it
Forecast Cost at Completion definition pending No formula agreed yet
Projects Completed this year 1 Processed = Y with DateFinish in this year

The panels

These work per project, from its Phase tab, with three amounts:

  • Due (PV) = planned amount of phases whose End Date has passed.
  • Done (EV) = planned amount of phases marked Complete.
  • Spent (AC) = the project's ProjectBalanceAmt.
Panel Sample shows What it means
Project Health Green 1, Amber 1, Red 1, No EVM data 6 No EVM data: nothing due yet. Green: Done is at least 90% of Due, and of Spent if there is any. Red: below 90% on all of them. Amber: mixed
Project Stage (no phase) 8, First Product Presentation 1 Count by the project's Standard Phase (C_Phase_ID). Your own stages are not mapped onto this yet
Physical vs Spent Physical USD 20%, BDT 0%. Spent 0% (the amounts spent are tiny) Physical = Done as a share of all phases' planned amount. Spent = ProjectBalanceAmt as a share of PlannedAmt. Payment-based progress is not in the ERP
Schedule Performance On Time 2, Delayed 1, At Risk 2, No schedule data 4, Average Delay 180 days No schedule data: no phase with both dates. At Risk: Done is under 90% of Due. Delayed: a phase not Complete is past its End Date. Average Delay is over At Risk and Delayed projects
Budget Status Within 1, Over 2, Not Started 6, Overrun USD 334.62, BDT 7.97 Not Started: nothing spent. Over: Spent is above Planned. Overrun is the excess

What is in the sample. Real documents on a test server, entered through iDempiere's own services, not invented figures. Most of the projects are test pushes of one building, so the amounts themselves mean nothing. What each one is there to show:

Project What was done in iDempiere Where it lands
HHS_VIEWER_PUSH_..840 All phases past due. 5 of 6 marked Complete Health Green, Schedule Delayed
HHS_VIEWER_PUSH_..809 All phases past due. Smallest marked Complete, material issued Health Amber, At Risk, Budget Within
SHED One phase past due, not Complete Health Red, At Risk
HHS_PLUGIN_POC Marked Commitment, Committed Amount on a line, one sales invoice Committed Cost, Invoiced
CAPEX_BDT_POC New project in BDT: Committed Amount, material issued, no budget BDT amounts, Budget Over, Overrun
Standard Material issued, no budget Budget Over, Overrun
HHS_VIEWER_PUSH_..730 Finish Date entered, then Close Project Closed, Completed this year. Not Active any more

The other views

Projects lists each project: Value, Name, Org, Currency, Planned, Actual, Committed, Standard Phase. The BIM button appears only when that project's building file is found, and opens it in the BIM viewer.

Projects view: one row per active project

Budget & Cost lists Planned, Committed, Invoiced and Actual per project.

Budget and Cost view

Approval Pending shows the count, 261 in the sample. Procurement Risks and Handover say definition pending: no agreed definition or source yet.

Page and Home tab: why a figure can differ

They use the same columns, but the page starts on Status Active Projects while the Home tab's money goals count every project, including inactive ones. Set Status to All and they agree:

Figure Page, Status Active Page, Status All Home tab goal
Approved Budget (USD) 24,982,203.77 39,971,166.17 39,971,166
Approved Budget (BDT) 15,139,265.67 30,286,701.64 30,286,702

If you know iDempiere

The Home tab side is made of windows you already have.

Dashboard piece iDempiere window Menu
One figure on the Home tab Performance Goal Performance Analysis and Accounting โ€บ Performance Measurement
What a goal measures Performance Measure same folder
The SQL behind it Performance Measure Calculation same folder
The dial's colours Performance Color Schema same folder
The panel itself Dashboard Content (Performance, shown at login) Organization Rules folder

Search any of these by name in the box at the top left (Alt+G).


The Home tab

  1. Log in as usual. The goals have no Role or User set, so every user of the tenant sees them.
  2. On Home, find the Performance panel, a narrow column at the far right.
  3. Click the panel's maximize button (top right of the panel). Your stock goals come first, then the 27 CAPEX goals.

The Performance panel maximized: stock goals first, then CAPEX goals on gray dials

Three kinds of dial

Dial Caption Used for How to read it
Gray A number Goals with no target Read the number. The needle stays at 0: it means nothing here
Green โ†’ Red A percent Cost against budget, lower is better Green up to 50%, yellow up to 100%, red beyond
Red โ†’ Green A percent Share of active projects, higher is better Red up to 50%, yellow up to 100%, green beyond

Gray dials for figures with no target, and green-to-red dials for cost against budget

Health and schedule goals: the good buckets as a share of active projects, the others as counts

Why only 9 of the 27 have a target

We followed what GardenWorld's own goals do: a plain plan number on the goal, and the colour schema that fits the direction. A target turns the caption into a percent and hides the number, so it is used only where the percent says more.

Goals Target Reads as
Actual Cost, Committed Cost, Invoiced (USD, BDT) Approved Budget: USD 39,971,166.17, BDT 30,286,701.64 Share of the budget used
Health Green, Schedule On Time, Budget Within Active projects: 9 On Time: 22% means 2 of 9
The other 18 None The number itself

The other 18 are the totals themselves, goals with no plan behind them (Completed this Year, Approval Pending, Average Delay, Overruns), and the bad buckets (Amber, Red, No EVM data, Delayed, At Risk, No schedule data, Over, Not started). A bad bucket with a target gets worse either way: on the stock schema, "33% of projects are red" would draw green.

These targets are the test server's own figures. Enter your own plan. A target is a fixed number, as on any stock goal, so when projects are added, "of 9" stays 9 until someone changes it.

The 27 goals

Projects and money:

Goal How it is worked out Counts inactive projects?
Total Projects All projects Yes
Closed Projects Processed = Y Yes
Active Projects IsActive = Y and Processed = N No
Approved Budget (USD, BDT) Sum of PlannedAmt Yes
Actual Cost (USD, BDT) Sum of ProjectBalanceAmt Yes
Committed Cost (USD, BDT) Sum of CommittedAmt Yes
Invoiced (USD, BDT) Sum of InvoicedAmt Yes
Projects Completed this Year Processed = Y, DateFinish in this year Yes
Approval Pending Workflow activities with WFState = OS and Processed = N, on any table n/a

Health, schedule and budget, active projects only, using Due, Done and Spent from The panels above:

Goal A project counts here when
Health No EVM data Nothing is due yet
Health Green Something is due, Done โ‰ฅ 90% of Due, and Spent is 0 or Done โ‰ฅ 90% of Spent
Health Amber Something is due, Spent is above 0, and only one of those two tests passes
Health Red Something is due, Done < 90% of Due, and Spent is 0 or Done < 90% of Spent
Schedule No schedule data No phase has both a Start and End Date
Schedule At Risk Has dated phases, something is due, and Done < 90% of Due
Schedule Delayed Has dated phases, not At Risk, and an unfinished phase is past its End Date
Schedule On Time Has dated phases, and neither At Risk nor Delayed
Schedule Average Delay (days) Over At Risk and Delayed projects: the average of each one's largest overdue days
Budget Not started Spent is 0
Budget Within Spent is not 0, and is at or below Planned
Budget Over Spent is above Planned
Budget Actual Overrun (USD, BDT) Total of Spent minus Planned over the Over projects

The 90% is the one rule a client stated. The rest are our working definitions, and you can change any of them: see Change what a goal counts.


What moves the numbers

Both places only read your project records. These are the iDempiere actions behind each figure, read from iDempiere's own code and tried on the test server:

Figure What moves it Where
Schedule goals Phases with Start Date and End Date Project window, Phase tab
Due, Done, Health Planned Amount on phases. Tick Complete when a phase finishes Phase tab
Actual Cost, Budget goals Issue material to the project Issue to Project
Committed Cost Tick Commitment on the project, then type Committed Amount on its lines Project window, Project Line tab
Invoiced Complete a sales invoice with the Project field set Sales Invoice and Credit/Debit Note
Closed Run Close Project Project window
Completed this Year Enter Finish Date, and close the project Project window

Three things that may surprise you:

  • A purchase order does not fill Committed Cost. iDempiere has no code that writes it from a PO, not even Generate PO from Project. It is typed in.
  • Close Project does not set the Finish Date. Without one, the project counts as Closed but not as Completed this Year.
  • Actual Cost is in your accounting currency, whatever the project's. Issue to Project adds the product's cost without converting it. On the test server, a BDT project shows 7.97, which is the USD cost. If you run projects in another currency, read that tile knowing this.

A measured example. On the test server, ticking Complete on SHED's one overdue phase moved five goals. It was then undone.

Home tab caption Before After
Health Green 11% 22%
Health Red 1 0
Schedule On Time 22% 33%
Schedule At Risk 2 1
Schedule Average Delay (days) 180 269

The average delay went up although a project improved: it left the average, and it had one of the shorter delays. Read that goal beside the At Risk and Delayed counts, not on its own.


Changing it

You need no developer for any of this. It changes the Home tab goals; the page's formulas stay as they are.

Set or change a target

  1. Open Performance Goal. Find the goal with the arrows or search.
  2. Enter Measure Target and pick a Color Schema that fits the direction. Save.

The Performance Goal window on CAPEX Actual Cost (USD): Measure Target, Color Schema and Measure Actual

The amount behind a percent stays visible here, in Measure Actual.

The first percent can be out of date

Saving a new target recalculates at once, but that first percent is scored against the previous target (standard iDempiere behaviour). The new target applies at the next refresh, see Troubleshooting.

Show a goal to fewer people

In Performance Goal, set Role or User/Contact. To hide it, clear Active. Your stock goals can be hidden the same way if you want only the CAPEX goals on Home.

Change what a goal counts

  1. Open Performance Measure Calculation and find the row with the goal's name.
  2. Edit Sql WHERE (or Sql SELECT). Save.

The Performance Measure Calculation window: Sql SELECT and Sql WHERE for CAPEX Active Projects

A broken SQL shows 0, not an error

iDempiere catches a measure's SQL error, logs it and returns 0. After any edit, check the number is what you expect. A sudden 0 may be your SQL.

To see a narrower population (one organization, for example), iDempiere offers the Restriction tab of Performance Goal. We have not tried it on these goals.

Change the dial's colours

Open Performance Color Schema. Each schema gives a colour up to Mark 1, up to Mark 2, and up to Mark 3.

The Performance Color Schema window: Green (50) - Yellow (100) - Red

Schema Tenant Editable by a tenant user?
Green (50) - Yellow (100) - Red System No
Red (50) - Yellow (100) - Green System No
No target (Gray) Yours Yes

To use other marks, add a schema in your tenant, then pick it in the goal's Color Schema field.

Add a goal

Add a row in Performance Measure Calculation, a Performance Measure that uses it, then a Performance Goal on that measure. To add a currency, copy an existing pair and change C_Currency_ID in Sql WHERE. We have edited targets through these windows and tested that; adding a goal by hand is standard iDempiere, but we have not run it for this dashboard.


Installing it

The Home tab goals

For an administrator with database access. On the test server these were applied with psql, in name order, followed by update_sequences.

Script Adds
202611031900_CAPEX-R0.sql The first measure: Approved Budget (USD)
202611032000_CAPEX-G2.sql The count and sum measures
202611032100_CAPEX-G3.sql A goal for each of them
202611032200_CAPEX-G4.sql The health, schedule and budget measures, and their goals
202611041000_CAPEX-G7.sql The targets and the gray colour schema

They are in the bim-ootb repository, under capex/legacy/migration/iD13/postgresql/, in iDempiere's own migration format. The first statement of each registers it in the migration log. Most carry a Restore line at the top that removes what they added. Goals calculate themselves the first time a Home tab shows them.

These scripts are written for GardenWorld

They set AD_Client_ID = 11, the currencies USD (100) and BDT (322), and this test server's target figures. Do not run them on your own tenant. Render your own from them instead, as below.

For your own tenant

capex/tools/site_migration.js writes your tenant's two scripts from the shipped ones. It never connects to your server.

  1. node capex/tools/site_migration.js --preflight <AD_Client_ID> prints a read-only SQL. Run it with psql -qtA and save the line it prints as preflight.json. It reports your roles, the currencies your projects hold and your next free ids.
  2. node capex/tools/site_migration.js preflight.json --role <AD_Role_ID> --out <folder>. Add --targets <file> to state your plan, for example {"budget":{"USD":1000},"activeProjects":3}.
  3. Apply the two scripts with psql in name order, run update_sequences(), and restart the server.

A goal with no target stated goes on the gray schema, so another company's numbers can never reach you. It refuses, and says why, if no role is given, if your projects hold no currency yet, or if these types or goals are already there.

Tested on a second tenant of a test server, through to that tenant's real Home tab. It has not been run on a real site.

The page

The page is plain files (capex/index.html and what it loads), with no server of its own and nothing to install in iDempiere's code. Your iDempiere needs a read-only web-service read type for each of the 8 tables it reads, and a user allowed to use them. These come in one migration script, 202611042300_CAPEX-WS-READ.sql, under capex/legacy/ws/migration/iD13/postgresql/, for GardenWorld. For your own tenant, For your own tenant above writes it. Restart the server afterwards. The write types in capex/legacy/ws_testserver/ are for a test server only: do not install them on yours.

A small job beside your server reads iDempiere and writes the file the page opens:

BRIDGE_BASE=https://your-server BRIDGE_USER=... BRIDGE_PASS=... BRIDGE_CLIENT=... BRIDGE_ROLE=... BRIDGE_ORG=... BRIDGE_WH=... \
  node capex/tools/legacy_snapshot.js

It writes capex/legacy_snapshot.json. The password stays with the job: the file and the browser never hold it, and nothing is written to iDempiere. Run it on a schedule. The page shows what the last run saw. Add ?source=legacy to the page's address to open on your data.

The file holds your project figures

Whoever can open the page can read them. Serve it only where you would show them.

The twin

Install the bundle capex/plugin/capex_dashboard.mjs in Plugins & Releases: it brings the same goal rows as the scripts above. To bring your rows in, run the same job with this exact file name beside the app:

node capex/tools/legacy_snapshot.js capex/site_copy.json

That name makes the job keep every column. The twin copies the file in at each start. It does not write to iDempiere, and the bundle is built for GardenWorld: a tenant other than that needs its tenant in the twin first, which has not been built.


What it does not do yet

Topic Today
Forecast Cost at Completion No agreed formula: says definition pending
Procurement Risks, Handover No agreed definition: says definition pending
Project Stage Shows the Standard Phase. How your stages map onto C_Phase is not agreed
Payment-based progress Not in the ERP
Project Stage, Physical vs Spent, project lists on the Home tab Page only, not goals
Other currencies on the Home tab No money goal covers them until you add one. The page shows each currency it finds

Still 0 on the test server: Invoiced (BDT). It has no BDT price list or USD-to-BDT rate, so a sales invoice can't reach a BDT project. Every other goal has counted real documents.

Check Approval Pending against your own meaning of "approval". It counts every suspended workflow activity. On the test server all 261 are on Business Partner, not on project documents.


How it was checked

  • Every tile drawn on the page equals the formula run separately over the sample's rows (19 of 19, at Status Active and All).
  • Every CAPEX caption on the test server's real Home tab equals the twin's, all 27.
  • For 26 of the 27 goals, Home tab values equal iDempiere's own goals, recalculated just before comparing. The other, Invoiced (BDT), is 0 on both sides, which proves nothing.
  • iDempiere's calculation, the twin's and the page's own formulas agree on the same rows.
  • A goal's stored value behaves the same on iDempiere and the twin: the caption holds inside the refresh interval, and moves after it, in three steps compared exactly.
  • The read types, built from their script alone on a clean server, each answered a real call. A write through a read type is refused.
  • A real edit in iDempiere reached the twin after the next job and reload, changing exactly one row, and was undone.

Not checked: a site larger than this test server. If the job stops, the copy just goes quietly out of date.


Troubleshooting

You see Why What to do
A gray dial at 0% That goal has no target Read the number in the caption
A percent, and you want the amount A target hides the number Open the goal: Measure Actual
A share over 100% The target is fixed, and projects were added Update Measure Target
A number looks out of date A goal recalculates only when a Home tab shows it and its value is over 30 minutes old. We saw one still showing 318.68 when the real figure was 334.62 Wait, or set ZK_DASHBOARD_PERFORMANCE_REFRESH_INTERVAL (milliseconds, default 1800000) in System Configurator
I changed the SQL and nothing moved Only saving a goal's target or scope recalculates at once Wait for the refresh
A goal suddenly reads 0 The SQL may be broken: errors show as 0 Check Sql WHERE and the server log
Page and Home tab budgets differ The page starts on Status Active, the goals count inactive projects too Set Status to All
Page shows old figures The job has not run since. Check Last Updated Run the job
The page has no B ยท Legacy iDempiere source The job's file is not beside the page Run the job, or check where it wrote
A project is missing from every Home tab money goal Its currency is not USD or BDT Add a goal for that currency
The panel is hard to read It is a narrow column Use the panel's maximize button

Related guides: Kernel-ERP User Guide ยท Distributed ERP.